12 S TOLUCA ESTATES DR 91602

Certificate Information: 12 S TOLUCA ESTATES DR 91602

Application / Permit
22010-30000-01840
Plan Check / Job No.
B22WL01416
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 2-STORY TYPE VB ACCESSORY LIVING QUARTERS (ALQ).
Permit Issued
Issued on 12/27/2022
Issuing Office
West Los Angeles
Current Status
Issued on 12/27/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 SERGIO SILVA
Corrections Issued 5/6/2022 SERGIO SILVA
Quality Review Completed 5/12/2022 CHIHARU SUZUKI
Applicant returned to address corrections 10/25/2022 SERGIO SILVA
Building Plans Picked Up 10/27/2022 APPLICANT
Applicant returned to address corrections 11/14/2022 SERGIO SILVA
Plan Check Approved 11/30/2022 SERGIO SILVA
Issued 12/27/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/8/2022 MEGAN GODINEZ
Sewer availability Cleared 7/8/2022 MEGAN GODINEZ
Private street Cleared 8/10/2022 STEVEN WECHSLER
ZI Cleared 8/10/2022 STEVEN WECHSLER
Hydrant and Access approval Cleared 8/24/2022 JOHN CONNEALLY
Low Impact Development Cleared 10/21/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/24/2022 CARLOS AGUILERA
Miscellaneous Cleared 10/26/2022 SERGIO SILVA

Contact Information

Architect Giannetti,, Stephen Andrew; Lic. No.: C18467 851 SADDLE LANE      OJAI, CA 93023
Contractor Jones Builders Group Inc; Lic. No.: 904861-B 23823 MALIBU RD 50-375      MALIBU, CA 90265
Engineer Cattan,, Christian George; Lic. No.: C82566 8444 OWENSMOUTH AVE      CANOGA PARK, CA 91304
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Lycklama,, James Heinz; Lic. No.: L7525 32218 N BIG OAK LN      CASTAIC, CA 91384
Engineer Wang,, Guan; Lic. No.: C79702 135 N SAN GABRIEL BLVD      SAN GABRIEL, CA 91775
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 5/5/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 6/5/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Conditional Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 12/4/2023 Not Ready for Inspection KIRK SANDERS
Drywall Nailing 1/17/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Approved KIRK SANDERS
Green Building Rough 1/17/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 3/4/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/4/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 4/15/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 4/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 4/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Steel/Welding 4/19/2024 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 4/23/2024 Conditional Approval JUAN VALENZUELA
HVAC-Rough 8/12/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/6/2024 Partial Approval CHRISTOPHER ROJAS
Shower Pan 11/8/2024 Corrections Issued CHRISTOPHER ROJAS
Shower Pan 11/21/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/11/2024 Partial Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/13/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/4/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/28/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 2/28/2025 Approved GAREN HAYRAPETYAN
Insulation 2/28/2025 Corrections Issued GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 2/28/2025 Approved GAREN HAYRAPETYAN
Wood Frame 2/28/2025 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/4/2025 Approved CHRISTOPHER ROJAS
Insulation 3/4/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/21/2025 Approved CHRISTOPHER ROJAS
Sewer 4/29/2025 Approved JAVIER RAMOS JR
Underground Mechanical 4/29/2025 Partial Approval JAVIER RAMOS JR
HVAC-Final 3/9/2026 Approved JAVIER RAMOS JR
Gas Test 4/20/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/20/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/4/2026 Approved JAVIER RAMOS JR