12 S TOLUCA ESTATES DR 91602
Certificate Information: 12 S TOLUCA ESTATES DR 91602
- Application / Permit
- 22010-30000-01838
- Plan Check / Job No.
- B22WL01416
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 12/27/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | SERGIO SILVA |
| Corrections Issued | 5/6/2022 | SERGIO SILVA |
| Quality Review Completed | 5/12/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/25/2022 | SERGIO SILVA |
| Building Plans Picked Up | 10/27/2022 | APPLICANT |
| Applicant returned to address corrections | 11/14/2022 | SERGIO SILVA |
| Plan Check Approved | 11/30/2022 | SERGIO SILVA |
| Issued | 12/27/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2022 | MEGAN GODINEZ |
| Permit | Cleared | 6/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/8/2022 | MEGAN GODINEZ |
| Private street | Cleared | 8/10/2022 | STEVEN WECHSLER |
| ZI | Cleared | 8/10/2022 | STEVEN WECHSLER |
| Trees in Parkway | Cleared | 8/11/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 8/24/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 10/21/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/24/2022 | CARLOS AGUILERA |
| Excavation more than 5-ft deep | Cleared | 10/26/2022 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 10/26/2022 | SERGIO SILVA |
Contact Information
| Architect | Giannetti,, Stephen Andrew; Lic. No.: C18467 | 851 SADDLE LANE OJAI, CA 93023 |
| Contractor | Jones Builders Group Inc; Lic. No.: 904861-B | 23823 MALIBU RD 50-375 MALIBU, CA 90265 |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Lycklama,, James Heinz; Lic. No.: L7525 | 32218 N BIG OAK LN CASTAIC, CA 91384 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/22/2023 | Partial Inspection | JACK KARGODORIAN |
| Deputy Steel/Welding | 6/7/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/16/2023 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 7/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Reinforced Concrete Frame | 7/19/2023 | Partial Approval | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Steel/Welding | 8/31/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 9/1/2023 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 9/18/2023 | Conditional Approval | DAVID MATSON |
| Deputy Reinf. Concrete | 9/18/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/19/2023 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 9/25/2023 | Conditional Approval | DAVID MATSON |
| Deputy Steel/Welding | 9/26/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 9/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 10/5/2023 | Conditional Approval | DAVID MATSON |
| Deputy Reinf. Concrete | 10/5/2023 | Conditional Approval | DAVID MATSON |
| Deputy Steel/Welding | 10/5/2023 | Conditional Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 10/6/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 10/6/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/6/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 10/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 10/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 10/17/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/24/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 4/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/21/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 5/21/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/31/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/31/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 10/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/8/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 11/8/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 11/21/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/11/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 12/11/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 12/11/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 12/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/13/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 2/18/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/18/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 2/28/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Wood Frame | 2/28/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 3/4/2025 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 3/4/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/21/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/10/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 4/29/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/29/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 5/12/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 5/23/2025 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 5/23/2025 | Partial Approval | RYAN SALAZAR |
| Gas Test | 5/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 5/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 5/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 6/3/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 6/17/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/26/2025 | Approved | JAVIER RAMOS JR |
| Deputy Steel/Welding | 7/18/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Structural Steel Frame | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 2/19/2026 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Final | 3/9/2026 | Approved | JAVIER RAMOS JR |
| Gas Test | 4/20/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/20/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/4/2026 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 5/4/2026 | Approved | JAVIER RAMOS JR |