13544 W D'ESTE DR 90272
Certificate Information: 13544 W D'ESTE DR 90272
- Application / Permit
- 22010-30000-01538
- Plan Check / Job No.
- B22WL01220
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story residence with basement below and attached 3-car garage
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | TARIK SAOUD |
| Corrections Issued | 5/4/2022 | TARIK SAOUD |
| Quality Review Completed | 5/9/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 8/5/2022 | TARIK SAOUD |
| Plan Check Approved | 8/9/2022 | TARIK SAOUD |
| Building Plans Picked Up | 8/9/2022 | APPLICANT |
| Issued | 1/19/2023 | APPLICANT |
| CofO in Progress | 2/5/2026 | KEVIN SARGSYAN |
| CofO in Progress | 2/9/2026 | KEVIN SARGSYAN |
| No Progress | 2/9/2026 | KEVIN SARGSYAN |
| CofO in Progress | 2/9/2026 | KEVIN SARGSYAN |
| CofO in Progress | 3/10/2026 | KEVIN SARGSYAN |
| Permit Finaled | 3/12/2026 | RICHARD STEINBACH |
| CofO Issued | 3/12/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/12/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 5/16/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 5/19/2022 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 5/24/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 7/7/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 7/22/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/26/2022 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 8/5/2022 | TARIK SAOUD |
Contact Information
| Architect | Ungar,, Kenneth Joel; Lic. No.: C21777 | 1173 WESTBEND ROAD WESTLAKE VILLAGE, CA 91362 |
| Contractor | Williams Craig R Construction Inc; Lic. No.: 479539-B | 2219 PONTIUS AVENUE LOS ANGELES, CA 90064 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Danz,, Joshua; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | Tani,, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2023 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | KENNETH NAGLE |
| Underground Mechanical | 11/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 12/1/2023 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/4/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 12/29/2023 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/3/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 1/4/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 1/5/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 1/25/2024 | Conditional Approval | EVAN COOPER |
| Deputy Wood Construction | 2/8/2024 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 3/27/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/28/2024 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 3/29/2024 | Conditional Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/4/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/8/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 4/10/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 4/10/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/12/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 4/16/2024 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/17/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 4/25/2024 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/25/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/20/2024 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 7/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/3/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 9/4/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 9/4/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/11/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 10/1/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/12/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 11/19/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 11/19/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | KEVIN SARGSYAN |
| Insulation | 12/6/2024 | Approved | KENNETH NAGLE |
| Drywall Nailing | 12/19/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/31/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/6/2025 | Approved | JESUS RODRIGUEZ |
| Sewer | 3/3/2025 | Approved | KEVIN SARGSYAN |
| Gas Test | 3/11/2025 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/23/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/30/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 10/1/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/8/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 10/9/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/14/2025 | Partial Approval | HERBERT GIRON |
| PLUMBING-Final | 10/16/2025 | Approved | KEVIN SARGSYAN |
| Gas Test | 10/23/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/27/2025 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 11/3/2025 | Approved | KENNETH NAGLE |
| HVAC-Final | 11/17/2025 | Approved | KEVIN SARGSYAN |
| Green Building Final | 12/10/2025 | Approved | KEVIN SARGSYAN |
| Final | 2/5/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 2/5/2026 | Approved | KEVIN SARGSYAN |
| Structural Steel Frame | 2/5/2026 | Approved | KEVIN SARGSYAN |