23455 W COLLINS ST 91367
Certificate Information: 23455 W COLLINS ST 91367
- Application / Permit
- 22010-30000-01510
- Plan Check / Job No.
- B22WL01182
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-Story S.F.D w/Attached Garage ** 1 of 4 **
- Permit Issued
- Issued on 10/15/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | DAVID CASTILLO |
| Corrections Issued | 4/26/2022 | DAVID CASTILLO |
| Quality Review Completed | 4/26/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 5/31/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/3/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/29/2022 | DAVID CASTILLO |
| Plan Check Approved | 8/17/2022 | DAVID CASTILLO |
| Issued | 10/15/2022 | APPLICANT |
| Building Plans Picked Up | 10/17/2022 | APPLICANT |
| CofO in Progress | 8/29/2024 | TROY SANDERS |
| Permit Finaled | 9/17/2024 | JOHN JANSON |
| CofO Issued | 9/17/2024 | JOHN JANSON |
| Permit Finaled | 9/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/4/2022 | KIRK LINKLATER |
| Address approval | Cleared | 5/11/2022 | DAGOVERTO GUERRERO |
| Permit | Cleared | 5/11/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/12/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 6/6/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 6/6/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 7/21/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/22/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 7/29/2022 | DAVID CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2022 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Corrections Issued | TROY SANDERS |
| Pre-Inspection | 3/2/2023 | Approved | TROY SANDERS |
| Special/Order Compliance | 3/2/2023 | Partial Inspection | MORRIS JACKSON |
| Deputy Reinf. Concrete | 4/12/2023 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 4/12/2023 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Partial Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 4/28/2023 | Partial Approval | TROY SANDERS |
| Deputy Steel/Welding | 5/5/2023 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 7/25/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 7/28/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/24/2023 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | TROY SANDERS |
| Green Building Rough | 8/24/2023 | Not Ready for Inspection | TROY SANDERS |
| Verify Sprinkler Sign Off | 8/24/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/30/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 8/30/2023 | Approved | TROY SANDERS |
| Green Building Rough | 8/30/2023 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 10/11/2023 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | HORACE FULTZ |
| Green Building Rough | 10/13/2023 | Approved | HORACE FULTZ |
| Shower Pan | 10/13/2023 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 10/18/2023 | Partial Approval | TROY SANDERS |
| Shower Pan | 10/18/2023 | Approved | TROY SANDERS |
| Wood Frame | 10/18/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 10/26/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/26/2023 | Partial Approval | TROY SANDERS |
| Gas Test | 11/20/2023 | Not Ready for Inspection | TROY SANDERS |
| Gas Test | 11/29/2023 | Approved | TROY SANDERS |
| HVAC-Final | 8/8/2024 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Final | 8/12/2024 | Approved | TROY SANDERS |
| HVAC-Final | 8/12/2024 | Approved | TROY SANDERS |
| Service/Power Release | 8/12/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Final | 8/22/2024 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 8/22/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/22/2024 | Approved | TROY SANDERS |
| Final | 8/27/2024 | Not Ready for Inspection | TROY SANDERS |
| Final | 8/28/2024 | OK to Issue CofO | TROY SANDERS |