12737 W MITCHELL AVE 90066

Certificate Information: 12737 W MITCHELL AVE 90066

Application / Permit
22010-30000-01417
Plan Check / Job No.
B22WL01098
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
new 15 unit apartment, 5 story above 1 story podium building with parking on ground floor.
Permit Issued
Issued on 4/20/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 KAVIAN REFAHI
Corrections Issued 4/12/2022 KAVIAN REFAHI
Quality Review Completed 4/19/2022 CHIHARU SUZUKI
Building Plans Picked Up 6/1/2022 APPLICANT
Disabled Access Plans Picked Up 6/3/2022 APPLICANT
Applicant returned to address corrections 6/10/2022 KAVIAN REFAHI
Applicant returned to address corrections 6/24/2022 KAVIAN REFAHI
Applicant returned to address corrections 11/14/2022 KAVIAN REFAHI
Applicant returned to address corrections 12/5/2022 KAVIAN REFAHI
Applicant returned to address corrections 12/23/2022 KAVIAN REFAHI
Plan Check Approved 4/19/2023 KAVIAN REFAHI
Issued 4/20/2023 APPLICANT
CofO in Progress 5/21/2025 DERRICK SPENCER
No Progress 5/22/2025 DAVID TSAU
CofO in Progress 5/22/2025 DAVID TSAU
Permit Finaled 5/22/2025 HENRY BAGHDASSARIAN
CofO Issued 5/22/2025 HENRY BAGHDASSARIAN
Permit Finaled 5/22/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 6/1/2022 TRACY TATE
Permit Cleared 6/1/2022 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 6/2/2022 TRACY TATE
Sewer availability Cleared 6/2/2022 TRACY TATE
Trees in Parkway Cleared 6/10/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 9/19/2022 KURT CORRAL
Miscellaneous Cleared 11/17/2022 RUBEN VASQUEZ
Green Code Cleared 12/8/2022 MICHAEL AYERS
Low Impact Development Cleared 2/17/2023 ORVAL HERNANDEZ-MARCI
Fire Marshal Fire Life Safety Cleared 2/21/2023 MENOA AGHAJANI
Roof/Waste drainage to street Cleared 2/23/2023 DINAH GARIN
DAS Clearance Cleared 3/8/2023 EDDIE GARIN
DCP conditions approval Cleared 3/29/2023 LOUIE MILLER
Density Bonus 12.22.A.25 Cleared 3/29/2023 LOUIE MILLER
Density Bonus 12.22.A.25 Cleared 3/29/2023 LOUIE MILLER
Frnt yard landscape/Water mgmt Cleared 4/11/2023 RUBEN VASQUEZ
Miscellaneous Cleared 4/11/2023 RUBEN VASQUEZ
Miscellaneous Cleared 4/11/2023 RUBEN VASQUEZ
Miscellaneous Cleared 4/11/2023 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 4/11/2023 RUBEN VASQUEZ
Driveway location Cleared 4/13/2023 FREDDY GARCIA
Specific Plan Cleared 4/13/2023 FREDDY GARCIA

Contact Information

Architect Daham,, Ramsey Walid; Lic. No.: C34257 127 ARENA STREET      EL SEGUNDO, CA 90245
Contractor Owner-Builder       ,
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/24/2023 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 4/24/2023 Not Ready for Inspection DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Rough 5/15/2023 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 5/15/2023 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 5/15/2023 Not Ready for Inspection DERRICK SPENCER
Verify Sprinkler Sign Off 5/15/2023 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 5/17/2023 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/9/2023 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 6/12/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/3/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 9/8/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 9/13/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 9/29/2023 Not Ready for Inspection DERRICK SPENCER
Masonry Wall/Backfill 9/29/2023 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 10/3/2023 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 10/4/2023 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 10/20/2023 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 10/31/2023 Partial Approval DERRICK SPENCER
Wood Frame 11/14/2023 Partial Approval DERRICK SPENCER
Wood Frame 12/14/2023 Partial Approval DERRICK SPENCER
Deputy Wood Construction 1/22/2024 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Partial Approval DERRICK SPENCER
Deputy Wood Construction 2/21/2024 Approved DERRICK SPENCER
Wood Frame 2/21/2024 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Partial Approval DERRICK SPENCER
Deputy Wood Construction 4/5/2024 Conditional Approval PAUL DAVIDSON
Drywall Nailing 4/5/2024 Partial Inspection PAUL DAVIDSON
Wood Frame 4/5/2024 Partial Approval PAUL DAVIDSON
Insulation 4/9/2024 Partial Approval DERRICK SPENCER
Wood Frame 4/9/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 4/17/2024 Partial Approval DERRICK SPENCER
Wood Frame 4/17/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 4/25/2024 Partial Approval DERRICK SPENCER
Insulation 4/25/2024 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 5/17/2024 Approved DERRICK SPENCER
Wood Frame 5/28/2024 Partial Approval DERRICK SPENCER
Insulation 6/3/2024 Partial Approval PAUL DAVIDSON
Deputy Wood Construction 7/2/2024 Approved DERRICK SPENCER
Wood Frame 7/5/2024 Partial Approval DERRICK SPENCER
Wood Frame 7/11/2024 Partial Approval DERRICK SPENCER
Insulation 7/17/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 8/5/2024 Approved DERRICK SPENCER
Wood Frame 8/5/2024 Partial Approval DERRICK SPENCER
Insulation 8/8/2024 Partial Approval PAUL DAVIDSON
Insulation 8/12/2024 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/12/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 8/15/2024 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/15/2024 Approved DERRICK SPENCER
Drywall Nailing 8/20/2024 Partial Approval DERRICK SPENCER
Wood Frame 8/20/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 8/23/2024 Partial Approval DERRICK SPENCER
Insulation 8/23/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 8/27/2024 Partial Approval DERRICK SPENCER
Insulation 8/27/2024 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 8/27/2024 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 8/30/2024 Approved DERRICK SPENCER
Light Gage Steel Frame 8/30/2024 Approved DERRICK SPENCER
Drywall Nailing 9/12/2024 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 9/12/2024 Approved DERRICK SPENCER
Wood Frame 9/12/2024 Partial Approval DERRICK SPENCER
Green Building Rough 9/17/2024 Approved DERRICK SPENCER
Insulation 9/17/2024 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 9/17/2024 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 9/17/2024 Approved DERRICK SPENCER
Interior/Exterior Lathing 12/9/2024 Approved DERRICK SPENCER
Footing/Foundation/Slab 2/21/2025 Approved DERRICK SPENCER
Final 4/9/2025 Not Ready for Inspection DERRICK SPENCER
Green Building Final 4/9/2025 Approved DERRICK SPENCER
Reinforced Concrete Frame 4/9/2025 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved DERRICK SPENCER
Smoke Detectors 4/9/2025 Approved DERRICK SPENCER
Final 4/16/2025 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 4/16/2025 Approved DERRICK SPENCER
Insulation 4/24/2025 Approved DERRICK SPENCER
Special/Order Compliance 4/24/2025 Approved DERRICK SPENCER
Final 4/25/2025 Not Ready for Inspection DERRICK SPENCER
Final 4/28/2025 OK to Issue CofO DERRICK SPENCER