20233 3/4 N GATES ST 90031
Certificate Information: 20233 3/4 N GATES ST 90031
- Application / Permit
- 22010-30000-01395
- Plan Check / Job No.
- B22WL01044
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU w/ roof deck per ordinace
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 4/5/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 4/7/2022 | CHIHARU SUZUKI |
| Disabled Access Plans Picked Up | 5/6/2022 | APPLICANT |
| Applicant returned to address corrections | 9/16/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 11/3/2022 | YASHAR EMAMI |
| Building Plans Picked Up | 11/3/2022 | APPLICANT |
| Plan Check Approved | 11/23/2022 | YASHAR EMAMI |
| Issued | 1/31/2023 | APPLICANT |
| CofO in Progress | 1/9/2024 | OSVALDO PARAMO |
| CofO in Progress | 1/9/2024 | OSVALDO PARAMO |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 6/30/2022 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/26/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 9/16/2022 | ROGELIO CORTES |
| Tenant Habitability Plan | Cleared | 9/21/2022 | MICHAEL SOTO |
| Roof/Waste drainage to street | Cleared | 9/23/2022 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 10/4/2022 | ANACANY HURTADO |
| DAS Clearance | Cleared | 10/18/2022 | EDDIE GARIN |
Contact Information
| Contractor | Yakov Design & Build; Lic. No.: 1067993-B | 8055 W MANCHESTER AVE 510 PLAYA DEL REY, CA 90293 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/8/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 3/23/2023 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 3/24/2023 | No Access for Inspection | RICHARD DOCKUS |
| Insulation | 3/24/2023 | No Access for Inspection | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 3/24/2023 | No Access for Inspection | RICHARD DOCKUS |
| Wood Frame | 3/24/2023 | No Access for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 5/15/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 5/24/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/24/2023 | Partial Approval | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/24/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 5/24/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 6/6/2023 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 6/6/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 6/6/2023 | Approved | OSVALDO PARAMO |
| Insulation | 7/11/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/11/2023 | Conditional Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 8/9/2023 | No Access for Inspection | AMY COLIN |
| Interior/Exterior Lathing | 8/9/2023 | No Access for Inspection | AMY COLIN |
| Drywall Nailing | 8/11/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/11/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 10/27/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 10/27/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/27/2023 | Approved | OSVALDO PARAMO |
| Final | 11/7/2023 | Corrections Issued | OSVALDO PARAMO |
| Final | 12/18/2023 | Corrections Issued | OSVALDO PARAMO |
| Final | 1/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 1/8/2024 | OK to Issue CofO | OSVALDO PARAMO |