10740 W VANOWEN ST 91605

Certificate Information: 10740 W VANOWEN ST 91605

Application / Permit
22010-30000-01390
Plan Check / Job No.
B22WL01036
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
new 2 story building, 1st floor market and 2nd floor office within existing gas station
Permit Issued
Issued on 12/28/2022
Issuing Office
Valley
Current Status
Issued on 12/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 KAVIAN REFAHI
Corrections Issued 4/14/2022 KAVIAN REFAHI
Quality Review Completed 4/28/2022 CHIHARU SUZUKI
Disabled Access Plans Picked Up 4/28/2022 APPLICANT
Building Plans Picked Up 4/29/2022 APPLICANT
Plan Check Approved 12/1/2022 KAVIAN REFAHI
Issued 12/28/2022 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 4/19/2022 LOUIS ORTEGA
"Q" conditions Cleared 4/25/2022 LOUIS ORTEGA
Address approval Cleared 5/2/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/2/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 5/31/2022 KURT CORRAL
Highway dedication Cleared 6/8/2022 DAGOVERTO GUERRERO
Permit Cleared 6/8/2022 DAGOVERTO GUERRERO
DAS Clearance Cleared 7/20/2022 KAVIAN REFAHI
Low Impact Development Cleared 11/16/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/16/2022 CARLOS AGUILERA
Green Code Cleared 11/18/2022 RICHARD GARCIA
Food establishment approval Cleared 12/1/2022 LACDHS APPROVED

Contact Information

Architect Manligas,, Amorsolo Rubio; Lic. No.: C15983 1120 LITTLE ROCK WAY      LAS VEGAS, NV 89123
Contractor Superior Construction; Lic. No.: 852082-B 16018 CIRCLE DIAMOND ROAD      SYLMAR, CA 91342
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2023 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/5/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 6/5/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 6/8/2023 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 6/13/2023 Conditional Approval JOHN KITCKO
Masonry Wall/Backfill 6/13/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 6/14/2023 Approved JOHN KITCKO
Deputy Steel/Welding 6/15/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 6/15/2023 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 7/25/2023 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 8/2/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 8/2/2023 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 8/3/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 8/4/2023 Conditional Approval JEFFREY DURAN
Green Building Rough 8/8/2023 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 8/8/2023 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 8/8/2023 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Masonry 8/15/2023 Approved JOHN KITCKO
Masonry Wall/Backfill 8/16/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 8/17/2023 Approved JOHN KITCKO
Masonry Wall/Backfill 8/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 8/22/2023 Approved JOHN KITCKO
Green Building Rough 8/22/2023 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 8/22/2023 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 8/22/2023 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Masonry 8/23/2023 Approved JOHN KITCKO
Deputy Reinf. Masonry 8/25/2023 Approved JOHN KITCKO
Masonry Wall/Backfill 8/25/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 8/28/2023 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 8/29/2023 Approved JOHN KITCKO
Deputy Steel/Welding 8/31/2023 Approved JOHN KITCKO
Deputy Steel/Welding 9/8/2023 Approved JOHN KITCKO
Deputy Wood Construction 9/13/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval JOHN KITCKO
Green Building Rough 9/14/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 9/14/2023 Approved JOHN KITCKO
Wood Frame 9/14/2023 Partial Approval JOHN KITCKO
Green Building Rough 9/27/2023 Not Ready for Inspection JOHN KITCKO
Light Gage Steel Frame 9/27/2023 Partial Approval JOHN KITCKO
Wood Frame 9/27/2023 Partial Approval JOHN KITCKO
Green Building Rough 10/13/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/13/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 10/19/2023 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 10/23/2023 Partial Approval JOHN KITCKO
Insulation 11/9/2023 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 11/9/2023 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 11/13/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 12/26/2023 Approved JOHN KITCKO
Drywall Nailing 12/26/2023 Partial Approval JOHN KITCKO
Drywall Nailing 12/29/2023 Approved JOHN KITCKO
T-Bar Ceiling 2/1/2024 Corrections Issued ROBERT DAVIS
Interior/Exterior Lathing 3/8/2024 Not Ready for Inspection JOHN KITCKO
T-Bar Ceiling 3/8/2024 Partial Approval JOHN KITCKO
T-Bar Ceiling 3/21/2024 Approved JOHN KITCKO
Footing/Foundation/Slab 11/14/2024 Partial Approval JOHN KITCKO
Final 1/10/2025 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 1/10/2025 Approved JOHN KITCKO
Green Building Final 1/10/2025 Approved JOHN KITCKO
Green Building Rough 1/10/2025 Approved JOHN KITCKO
Reinforced Masonry Frame 1/10/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Approved JOHN KITCKO
Smoke Detectors 1/10/2025 Approved JOHN KITCKO
Structural Steel Frame 1/10/2025 Approved JOHN KITCKO
Wood Frame 1/10/2025 Approved JOHN KITCKO
Final 3/5/2025 Partial Inspection JOHN KITCKO
Special/Order Compliance 2/19/2026 Partial Inspection DEANDRE HOFFMAN