1344 N CHAUTAUQUA BLVD 90272
Certificate Information: 1344 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 22010-30000-01199
- Plan Check / Job No.
- B22WL00944
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story S.F.D. with basement and attached garage. *** 1 of 5 ***
- Permit Issued
- Issued on 2/23/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/23/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | KAVIAN REFAHI |
| Corrections Issued | 4/14/2022 | KAVIAN REFAHI |
| Quality Review Completed | 4/15/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Applicant returned to address corrections | 6/6/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 6/30/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/7/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/19/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/14/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/23/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 11/28/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/6/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/8/2023 | KAVIAN REFAHI |
| Plan Check Approved | 2/21/2023 | KAVIAN REFAHI |
| Issued | 2/23/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Permit | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 8/15/2022 | ADALBERTO VERA |
| Landscape for retaining wall | Cleared | 8/22/2022 | RYAN LY |
| GPI Written Notices | Cleared | 10/14/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 10/14/2022 | KAVIAN REFAHI |
| Low Impact Development | Cleared | 11/23/2022 | MARCO SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 11/28/2022 | CALOSHA APPROVED |
| Roof/Waste drainage to street | Cleared | 11/28/2022 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 11/29/2022 | RUEL COLE |
| Work Adjacent to Public Way | Cleared | 1/13/2023 | SAUL GARCIA |
Contact Information
| Contractor | Gibson Gordon S Inc; Lic. No.: 524012-B | 3000 31ST STREET SUITE G SANTA MONICA, CA 90405 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/5/2023 | Partial Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 12/5/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/14/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/17/2024 | Partial Approval | KENNETH NAGLE |
| Reinforced Concrete Frame | 2/9/2024 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 2/26/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/27/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/6/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 4/8/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Special/Order Compliance | 8/20/2024 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/22/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/3/2024 | Partial Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 9/5/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/16/2024 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/27/2024 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/1/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 10/11/2024 | Partial Approval | EVAN COOPER |
| Insulation | 10/16/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/7/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 11/14/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 11/27/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/23/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 4/23/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/23/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/12/2025 | Approved | KENNETH NAGLE |
| Shower Pan | 5/19/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| Insulation | 5/22/2025 | Partial Approval | MEL KHACHATOURIAN |
| Shower Pan | 5/22/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Shower Pan | 5/27/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/29/2025 | Partial Approval | TEMISTOCLES CAAL |
| Green Building Rough | 5/29/2025 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 5/29/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 5/29/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 6/11/2025 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 7/11/2025 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 7/21/2025 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 7/22/2025 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 8/18/2025 | Conditional Approval | BOBBY KEY |
| Insulation | 8/19/2025 | Partial Approval | KENNETH NAGLE |
| Drywall Nailing | 10/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 10/16/2025 | Partial Approval | KENNETH NAGLE |
| Wood Frame | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/5/2025 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/19/2025 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 12/19/2025 | Approved | TEMISTOCLES CAAL |
| Pre-Inspection | 3/12/2026 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/13/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 3/13/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 3/13/2026 | Approved | MICHAEL ALLEN |
| Gas Test | 3/25/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 3/31/2026 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 3/31/2026 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 4/21/2026 | Approved | TEMISTOCLES CAAL |