11620-11620 1/2 W HAMLIN ST 91606

Certificate Information: 11620-11620 1/2 W HAMLIN ST 91606

Application / Permit
22010-30000-00642
Plan Check / Job No.
B22WL00563
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(n) detached 1-story 2 unit ADUs per CA gov. code 65852.2 (E)(1)(D)
Permit Issued
Issued on 1/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 SERGIO SILVA
Corrections Issued 3/9/2022 SERGIO SILVA
Quality Review Completed 3/11/2022 FELIX FIGUEROA
Applicant returned to address corrections 8/22/2022 SERGIO SILVA
Building Plans Picked Up 8/25/2022 APPLICANT
Applicant returned to address corrections 11/9/2022 SERGIO SILVA
Plan Check Approved 11/16/2022 SERGIO SILVA
Issued 1/13/2023 APPLICANT
CofO in Progress 11/12/2025 ROBERTO PALACIOS-LOPEZ
CofO in Progress 12/4/2025 JUAN VALENZUELA
CofO in Progress 1/8/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 1/20/2026 RUBEN SALAS
CofO Issued 1/20/2026 RUBEN SALAS
Permit Finaled 1/20/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/25/2022 DWIGHT SANKEY
Address approval Cleared 6/22/2022 ROMAN GUTIERREZ
Permit Cleared 6/22/2022 ROMAN GUTIERREZ
Sewer availability Cleared 6/22/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/28/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 11/3/2022 ROMAN GUTIERREZ

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Architect Mcvay,, Bruce Cameron; Lic. No.: C11870 6440 E. EL ROBLE STREET      LONG BEACH, CA 90815
Contractor Quakestrong; Lic. No.: 1037437-B 1213 LA BREA AVENUE      LOS ANGELES, CA 90019

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/20/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/25/2023 Corrections Issued JOHN HAYES
Grounding or Bonding 4/25/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/26/2023 Approved DAVID MATSON
PLUMBING-Rough 5/16/2023 Corrections Issued ROBERT GOLD
Wood Frame 5/16/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 5/22/2023 Partial Approval JOHN HAYES
Green Building Rough 5/22/2023 Not Ready for Inspection JOHN HAYES
Insulation 5/22/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 5/22/2023 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 5/22/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/1/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/1/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/7/2024 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 7/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 7/2/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/3/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/3/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/11/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 3/11/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 3/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/17/2025 Approved MISAEL ESPARZA
Insulation 3/17/2025 Approved MISAEL ESPARZA
Drywall Nailing 3/20/2025 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 5/19/2025 No Access for Inspection JOSE AVILA
ELECTRICAL-Rough 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/11/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 8/1/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 8/1/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/1/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 9/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 10/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/29/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 11/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 11/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 12/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 1/5/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ