11620-11620 1/2 W HAMLIN ST 91606
Certificate Information: 11620-11620 1/2 W HAMLIN ST 91606
- Application / Permit
- 22010-30000-00642
- Plan Check / Job No.
- B22WL00563
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (n) detached 1-story 2 unit ADUs per CA gov. code 65852.2 (E)(1)(D)
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | SERGIO SILVA |
| Corrections Issued | 3/9/2022 | SERGIO SILVA |
| Quality Review Completed | 3/11/2022 | FELIX FIGUEROA |
| Applicant returned to address corrections | 8/22/2022 | SERGIO SILVA |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Applicant returned to address corrections | 11/9/2022 | SERGIO SILVA |
| Plan Check Approved | 11/16/2022 | SERGIO SILVA |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 11/12/2025 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 12/4/2025 | JUAN VALENZUELA |
| CofO in Progress | 1/8/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
| CofO Issued | 1/20/2026 | RUBEN SALAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/25/2022 | DWIGHT SANKEY |
| Address approval | Cleared | 6/22/2022 | ROMAN GUTIERREZ |
| Permit | Cleared | 6/22/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/22/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | ROMAN GUTIERREZ |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/20/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/25/2023 | Corrections Issued | JOHN HAYES |
| Grounding or Bonding | 4/25/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/26/2023 | Approved | DAVID MATSON |
| PLUMBING-Rough | 5/16/2023 | Corrections Issued | ROBERT GOLD |
| Wood Frame | 5/16/2023 | Corrections Issued | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/22/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 5/22/2023 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 5/22/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 5/22/2023 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 5/22/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/7/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 7/2/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/3/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/11/2025 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 3/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 3/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 3/17/2025 | Approved | MISAEL ESPARZA |
| Insulation | 3/17/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 3/20/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 5/19/2025 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 5/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 10/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 10/29/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 11/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 11/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 1/5/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |