12529 W WAGNER ST 90066
Certificate Information: 12529 W WAGNER ST 90066
- Application / Permit
- 22010-30000-00536
- Plan Check / Job No.
- B22WL00480
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD at rear of the lot per SB 9
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | REZA HAGHIGHAT |
| Corrections Issued | 2/19/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 3/9/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Applicant returned to address corrections | 12/5/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 5/22/2023 | REZA HAGHIGHAT |
| Issued | 7/27/2023 | APPLICANT |
| CofO in Progress | 2/24/2025 | MICHAEL ALLEN |
| CofO in Progress | 2/24/2025 | DAVID FEILER |
| No Progress | 2/24/2025 | DAVID FEILER |
| Permit Finaled | 6/5/2025 | RICHARD STEINBACH |
| CofO Issued | 6/5/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/5/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/11/2023 | REZA HAGHIGHAT |
| Miscellaneous | Cleared | 1/19/2023 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 1/19/2023 | MIGUEL GAMBOA |
| Senate Bill 9 | Cleared | 1/20/2023 | MIGUEL GAMBOA |
| Permit | Cleared | 1/25/2023 | JENSON LEE |
| Address approval | Cleared | 1/30/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/30/2023 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 2/1/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 2/17/2023 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 4/18/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/21/2023 | DINAH GARIN |
| Specific Plan | Cleared | 4/24/2023 | PEDRO AYALA |
| SB8 RUD | Cleared | 4/26/2023 | JESSICA WANG |
Contact Information
| Architect | Kienapfel,, Christian; Lic. No.: C31983 | PARAVANT ARCHITECTS 10866 WASHINGTON BLVD. STE. 110 CULVER CITY, CA 90232 |
| Contractor | Goliath Construction; Lic. No.: 1056541-B | 6914 RADFORD AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
| Geologist | , ; Lic. No.: GEO2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 9/12/2023 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 9/27/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/27/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/2/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 11/15/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 12/21/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/21/2023 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Sewer | 12/27/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/13/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 3/13/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 4/12/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 4/12/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 5/7/2024 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 5/15/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | TEMISTOCLES CAAL |
| Shower Pan | 5/22/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 7/2/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 10/17/2024 | Conditional Approval | TEMISTOCLES CAAL |
| HVAC-Final | 11/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 11/13/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/30/2025 | Approved | MICHAEL ALLEN |
| Final | 1/30/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 1/30/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Not Required | MICHAEL ALLEN |
| Service/Power Release | 1/30/2025 | Conditional Approval | MICHAEL ALLEN |
| Smoke Detectors | 1/30/2025 | Approved | MICHAEL ALLEN |
| Final | 2/21/2025 | OK to Issue CofO | MICHAEL ALLEN |
| Service/Power Release | 2/21/2025 | Approved | MICHAEL ALLEN |
| Deputy Reinf. Concrete | 3/17/2025 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 3/17/2025 | Corrections Issued | MICHAEL ALLEN |