9500 S BEACH ST 90002

Certificate Information: 9500 S BEACH ST 90002

Application / Permit
22010-30000-00364
Plan Check / Job No.
B22WL00220
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ADU AT THE REAR OF THE LOT. PER LAMC 12.22 A.33(c) AND (d). PER WFPP
Permit Issued
Issued on 2/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 ALFREDO JARA
Corrections Issued 2/4/2022 ALFREDO JARA
Building Plans Picked Up 2/16/2022 APPLICANT
Plan Check Approved 6/8/2022 ALFREDO JARA
Issued 2/7/2023 APPLICANT
CofO in Progress 7/7/2023 JOHN KLARIN
Permit Finaled 7/7/2023 ANSON MAGLASANG
CofO Issued 7/7/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/3/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/16/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 4/1/2022 JOSE HERNANDEZ
Low Impact Development Cleared 4/27/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/28/2022 JEANETTE VONG
Hydrant and Access approval Cleared 5/2/2022 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/21/2023 Partial Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 2/22/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 2/22/2023 Approved JOHN KLARIN
Sewer 2/22/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Approved JOHN KLARIN
HVAC-Rough 3/1/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/3/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 3/3/2023 Approved JAMES CHAVEZ
Green Building Rough 3/3/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 3/3/2023 Approved JAMES CHAVEZ
Underground Mechanical 3/3/2023 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 3/3/2023 Approved JAMES CHAVEZ
Insulation 3/7/2023 Approved JOHN KLARIN
Underground Mechanical 3/7/2023 Partial Approval JOHN KLARIN
Drywall Nailing 3/9/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 3/9/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 3/10/2023 Approved JOHN KLARIN
Underground Mechanical 3/10/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 3/21/2023 Approved JOHN KLARIN
ELECTRICAL-Final 5/5/2023 Approved JOHN KLARIN
Final 5/5/2023 Corrections Issued JOHN KLARIN
Gas Test 5/5/2023 Approved JOHN KLARIN
Green Building Final 5/5/2023 Approved JOHN KLARIN
HVAC-Final 5/5/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 5/5/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 5/5/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 5/5/2023 Approved JOHN KLARIN
ELECTRICAL-Final 5/8/2023 Approved JOHN KLARIN
Gas Test 5/8/2023 Approved JOHN KLARIN
HVAC-Final 5/8/2023 Approved JOHN KLARIN
PLUMBING-Final 5/8/2023 Approved JOHN KLARIN
Final 6/1/2023 Corrections Issued JOHN KLARIN
Service/Power Release 6/1/2023 Not Ready for Inspection JOHN KLARIN
Final 6/7/2023 Corrections Issued JOHN KLARIN
Service/Power Release 6/7/2023 Not Ready for Inspection JOHN KLARIN
Final 6/30/2023 Corrections Issued JOHN KLARIN
Service/Power Release 6/30/2023 Approved JOHN KLARIN
Final 7/7/2023 OK to Issue CofO JOHN KLARIN
Service/Power Release 7/7/2023 Approved JOHN KLARIN