659 E 90TH ST 90002

Certificate Information: 659 E 90TH ST 90002

Application / Permit
22010-30000-00363
Plan Check / Job No.
B22WL00218
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one story ADU with attached 1-car garage at rear of the lot per LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 MARJAN SHENASI
Corrections Issued 1/30/2022 MARJAN SHENASI
Plan Check Approved 5/24/2022 JAHANSHAH POURHASSAN
Building Plans Picked Up 5/25/2022 APPLICANT
Issued 6/6/2022 APPLICANT
CofO in Progress 10/27/2022 LILIANA PORTILLO
Permit Finaled 11/5/2022 DEROLD HAUFF
CofO Issued 11/5/2022 DEROLD HAUFF
Permit Finaled 11/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/7/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/30/2022 JEANETTE VONG
Sewer availability Cleared 3/30/2022 JEANETTE VONG
Low Impact Development Cleared 4/26/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/28/2022 JEANETTE VONG

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3627 E FIRST STREET      LOS ANGELES, CA 90063
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 6/23/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 6/28/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 7/26/2022 Approved ADAM ESCOTO
Gas Test 7/26/2022 Approved ADAM ESCOTO
HVAC-Rough 7/26/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/26/2022 Partial Approval ADAM ESCOTO
PLUMBING-Rough 7/26/2022 Approved ADAM ESCOTO
BUILDING-Rough-Frame 7/28/2022 Approved LILIANA PORTILLO
Green Building Rough 7/28/2022 Approved LILIANA PORTILLO
Sewer 7/28/2022 Approved LILIANA PORTILLO
Underground Mechanical 7/28/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 7/28/2022 Approved LILIANA PORTILLO
Insulation 8/2/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 8/8/2022 Corrections Issued LILIANA PORTILLO
Insulation 8/8/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/8/2022 Approved LILIANA PORTILLO
Drywall Nailing 10/7/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/7/2022 Corrections Issued LILIANA PORTILLO
Final 10/7/2022 Not Ready for Inspection LILIANA PORTILLO
Gas Test 10/7/2022 Approved LILIANA PORTILLO
Green Building Final 10/7/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 10/7/2022 Approved LILIANA PORTILLO
PLUMBING-Final 10/7/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/7/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 10/7/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 10/7/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/20/2022 Approved LILIANA PORTILLO
Final 10/20/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 10/20/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 10/20/2022 Not Ready for Inspection LILIANA PORTILLO
Final 10/27/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 10/27/2022 Approved LILIANA PORTILLO