659 E 90TH ST 90002
Certificate Information: 659 E 90TH ST 90002
- Application / Permit
- 22010-30000-00363
- Plan Check / Job No.
- B22WL00218
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New one story ADU with attached 1-car garage at rear of the lot per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | MARJAN SHENASI |
| Corrections Issued | 1/30/2022 | MARJAN SHENASI |
| Plan Check Approved | 5/24/2022 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 10/27/2022 | LILIANA PORTILLO |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 3/30/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 4/26/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | JEANETTE VONG |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 6/23/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/28/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/26/2022 | Approved | ADAM ESCOTO |
| Gas Test | 7/26/2022 | Approved | ADAM ESCOTO |
| HVAC-Rough | 7/26/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 7/26/2022 | Partial Approval | ADAM ESCOTO |
| PLUMBING-Rough | 7/26/2022 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 7/28/2022 | Approved | LILIANA PORTILLO |
| Sewer | 7/28/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 7/28/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 7/28/2022 | Approved | LILIANA PORTILLO |
| Insulation | 8/2/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 8/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 8/8/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/8/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/7/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 10/7/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Gas Test | 10/7/2022 | Approved | LILIANA PORTILLO |
| Green Building Final | 10/7/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/7/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/7/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/7/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 10/7/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 10/7/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/20/2022 | Approved | LILIANA PORTILLO |
| Final | 10/20/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/20/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 10/20/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 10/27/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 10/27/2022 | Approved | LILIANA PORTILLO |