2309 N HOLLYRIDGE DR 90068

Certificate Information: 2309 N HOLLYRIDGE DR 90068

Application / Permit
22010-30000-00358
Plan Check / Job No.
B22WL00204
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED (200 s.f) ONE STORY REC. ROOM
Permit Issued
Issued on 8/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 GARO TELMI
Corrections Issued 2/18/2022 GARO TELMI
Quality Review Completed 2/24/2022 KEN GILL
Building Plans Picked Up 3/1/2022 APPLICANT
Applicant returned to address corrections 6/29/2022 GARO TELMI
Plan Check Approved 8/24/2022 GARO TELMI
Issued 8/30/2022 APPLICANT
CofO in Progress 11/11/2023 JOAQUIN GREENOUGH
Permit Finaled 11/17/2023 DEROLD HAUFF
CofO Issued 11/17/2023 DEROLD HAUFF
Permit Finaled 11/17/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 3/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 3/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 3/19/2022 CINDY QI
Sewer availability Cleared 3/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/22/2022 CINDY QI
Hydrant and Access approval Cleared 5/21/2022 GILBERT URREA
Low Impact Development Cleared 5/31/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/5/2022 WALLIE JONG
Grading Pre-Inspection Cleared 8/24/2022 ALEXANDER HELFER

Contact Information

Architect , ; Lic. No.: C36966 260 E. MOUNTAIN VIEW ST      LONG BEACH, CA 90805
Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/8/2023 Partial Approval JOAQUIN GREENOUGH
Sewer 2/8/2023 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 2/8/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/10/2023 Partial Approval JOAQUIN GREENOUGH
Sewer 2/10/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/16/2023 Approved JOAQUIN GREENOUGH
Light Gage Steel Frame 2/16/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/6/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 6/6/2023 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Wood Construction 6/13/2023 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/16/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/16/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 6/16/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 6/16/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 6/16/2023 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/16/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/30/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 6/30/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 6/30/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/30/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 6/30/2023 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/30/2023 Approved JOAQUIN GREENOUGH
Insulation 7/28/2023 Approved STUART CHAPMAN
Deck 8/1/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 8/3/2023 Approved JOAQUIN GREENOUGH
Pre-Inspection 10/17/2023 Corrections Issued JOAQUIN GREENOUGH
Final 10/31/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/31/2023 Approved JOAQUIN GREENOUGH
Green Building Final 10/31/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 10/31/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 10/31/2023 Approved JOAQUIN GREENOUGH
Final 11/7/2023 Partial Inspection JOAQUIN GREENOUGH
Service/Power Release 11/7/2023 Approved JOAQUIN GREENOUGH
Final 11/11/2023 OK to Issue CofO JOAQUIN GREENOUGH