682 N ALMA REAL DR 90272
Certificate Information: 682 N ALMA REAL DR 90272
- Application / Permit
- 22010-30000-00190
- Plan Check / Job No.
- B22WL00115
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New (2) story single family home with basement, attached garage and trellis *** 1 of 3 ***
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Current Status
- Issued on 10/3/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 2/7/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 2/28/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 8/13/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/30/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 9/26/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 10/3/2022 | CHIHARU SUZUKI |
| Issued | 10/3/2022 | APPLICANT |
| Building Plans Picked Up | 10/4/2022 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/4/2022 | DWIGHT SANKEY |
| Permit | Cleared | 5/12/2022 | KATHLEEN LEE |
| ZA Case | Cleared | 5/12/2022 | DANIEL CORONADO |
| Sewer availability | Cleared | 5/16/2022 | KATHLEEN LEE |
| Trees in Parkway | Cleared | 6/2/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/4/2022 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2022 | KATHLEEN LEE |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | KATHLEEN LEE |
| Excavation more than 5-ft deep | Cleared | 8/30/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/30/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 8/30/2022 | FELIPE HERNANDEZ |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2022 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 12/15/2022 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 12/15/2022 | Approved | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 12/16/2022 | Conditional Approval | BRENDAN LOONEY |
| Deputy Shotcrete | 1/18/2023 | Conditional Approval | BRENDAN LOONEY |
| Reinforced Concrete Frame | 1/18/2023 | Corrections Issued | BRENDAN LOONEY |
| Reinforced Concrete Frame | 1/20/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 1/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 2/8/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/31/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/15/2023 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 9/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 10/11/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 2/23/2024 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Conditional Approval | EVAN COOPER |
| HVAC-Rough | 3/4/2024 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 3/4/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 3/20/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 3/20/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/28/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 4/11/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 4/16/2024 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/16/2024 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/10/2024 | Partial Approval | ARAM AVEDISIAN |