5919 W 78TH ST 90045
Certificate Information: 5919 W 78TH ST 90045
- Application / Permit
- 22010-30000-00029
- Plan Check / Job No.
- B22WL00025
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-Story ADU per LAMC 12.22A.33(c) and (d)
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | MANUEL GARCIA |
| Corrections Issued | 1/8/2022 | MANUEL GARCIA |
| Applicant returned to address corrections | 5/5/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/18/2022 | DAVID CASTILLO |
| Plan Check Approved | 8/24/2022 | DAVID CASTILLO |
| Issued | 8/25/2022 | APPLICANT |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| CofO in Progress | 10/11/2023 | BOBBY KEY |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 4/6/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 5/10/2022 | RIDWAN HARDY |
| ZA Case | Cleared | 6/15/2022 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 8/24/2022 | MANUEL GARCIA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/3/2022 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 1/19/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/19/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 1/24/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/26/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/31/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 2/1/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/17/2023 | Corrections Issued | BOBBY KEY |
| Wood Frame | 2/17/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 3/3/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 3/24/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | BOBBY KEY |
| Green Building Rough | 3/30/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/30/2023 | Partial Approval | BOBBY KEY |
| Insulation | 4/13/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/28/2023 | Conditional Approval | BOBBY KEY |
| Final | 7/28/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 7/28/2023 | Approved | BOBBY KEY |
| HVAC-Final | 7/28/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/28/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 7/28/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/11/2023 | Approved | BOBBY KEY |
| Final | 10/11/2023 | OK to Issue CofO | BOBBY KEY |