4634 N CEDROS AVE 91403
Certificate Information: 4634 N CEDROS AVE 91403
- Application / Permit
- 22010-20001-03109
- Plan Check / Job No.
- B23VN05360
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- SUPPLEMEMENTAL TO 22010-20000-03109 TO REVISE THE SCOPE OF WORK TO NEW 13' X 17'6" PATIO COVER WITH ATTACHED FULL BATHROOM WITH EXTERIOR ACCESS, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2023 | RARES BODEA |
| Corrections Issued | 4/26/2023 | RARES BODEA |
| Plan Check Approved | 5/16/2023 | RARES BODEA |
| Issued | 5/16/2023 | APPLICANT |
| Permit Finaled | 12/18/2023 | MISAEL ESPARZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/30/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 8/3/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 8/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 8/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 8/14/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Partial Approval | MISAEL ESPARZA |
| Insulation | 8/14/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/14/2023 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 8/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 8/17/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/17/2023 | Partial Approval | MISAEL ESPARZA |
| Pre-Inspection | 8/17/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/25/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/25/2023 | Approved | MISAEL ESPARZA |
| Final | 11/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 11/30/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 12/18/2023 | Permit Finaled | MISAEL ESPARZA |