7226 N RIVERTON AVE 91352
Certificate Information: 7226 N RIVERTON AVE 91352
- Application / Permit
- 22010-20001-02409
- Plan Check / Job No.
- B23VN08702
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ****ePlan**** Supplemental permit to # 22010-20000-02409 to change the slab on grade to raised foundation in ADU area and increase the height of bldg
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/14/2023
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 7/26/2023 | REZA HAGHIGHAT |
| Issued | 7/27/2023 | APPLICANT |
| Permit Finaled | 12/14/2023 | JOHN HAYES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 11/9/2023 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/21/2023 | Approved | JENNIFER RABUCHIN |
| Sewer | 11/21/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/7/2023 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Rough | 12/7/2023 | Partial Approval | ROBERT GOLD |
| Underground Mechanical | 12/7/2023 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 12/8/2023 | Partial Approval | ROBERT GOLD |
| Insulation | 12/8/2023 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 12/8/2023 | Partial Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 12/13/2023 | Conditional Approval | JUAN VALENZUELA |
| Final | 12/14/2023 | Permit Finaled | JOHN HAYES |
| Smoke Detectors | 12/14/2023 | Approved | JOHN HAYES |