12075 N RED HAWK LANE 91326
Certificate Information: 12075 N RED HAWK LANE 91326
- Application / Permit
- 22010-20001-01960
- Plan Check / Job No.
- B23VN00925
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR 22010-20000-01960 TO CONVERT 2-CAR GARAGE INTO SALES OFFICE & PORTION OF (11'-2" X 6') 1-CAR GARAGE INTO ADA BATHROOM
- Permit Issued
- Issued on 3/14/2023
- Issuing Office
- Current Status
- Issued on 3/14/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/21/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/23/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/23/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 2/23/2023 | APPLICANT |
| Plan Check Approved | 3/14/2023 | NILOOFAR MEHRAIN |
| Issued | 3/14/2023 | APPLICANT |
| Permit Closed-Status Void | 4/10/2024 | GREGORY POMISH |
| Re-Activate Permit | 12/19/2024 | GREGORY POMISH |
Permit Application Clearance Information
| "T" removal | Cleared | 2/24/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 2/24/2023 | BRENNEN OBETO |
| Sewer availability | Cleared | 2/24/2023 | LEE GUILBEAUX |
| Specific Plan | Cleared | 2/24/2023 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 2/24/2023 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 2/24/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 2/24/2023 | BRENNEN OBETO |
| ZI | Cleared | 2/24/2023 | BRENNEN OBETO |
| DAS Clearance | Cleared | 3/7/2023 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Wood Frame | 4/10/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 4/13/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 4/18/2023 | Partial Inspection | JEFFREY FULTON |
| Special/Order Compliance | 4/18/2023 | Partial Inspection | STEVEN LEVITT |
| Drywall Nailing | 6/9/2023 | Partial Inspection | JEFFREY FULTON |
| Final | 10/10/2023 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 10/10/2023 | Approved | JEFFREY FULTON |
| Final | 11/1/2023 | Partial Inspection | JEFFREY FULTON |
| Final | 11/6/2023 | Conditional Approval | JEFFREY FULTON |
| Final | 4/10/2024 | Partial Inspection | GREGORY POMISH |
| Final | 12/9/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 12/9/2025 | Partial Inspection | DEANDRE HOFFMAN |