11245 N NORRIS AVE 91331

Certificate Information: 11245 N NORRIS AVE 91331

Application / Permit
22010-20000-06703
Plan Check / Job No.
B22VN19193
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New detached 738 sq ft ADU.Per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 ofLAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 4/22/2024
Issuing Office
Current Status
Issued on 4/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 ALFREDO JARA
Corrections Issued 1/28/2023 ALFREDO JARA
Applicant returned to address corrections 4/5/2024 ALFREDO JARA
Plan Check Approved 4/21/2024 ALFREDO JARA
Issued 4/22/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 6/12/2023 RIDWAN HARDY
Construction within easement Cleared 6/12/2023 RIDWAN HARDY
Clean Up Green Up Cleared 8/17/2023 KENTON TRINH
ZI Cleared 8/17/2023 KENTON TRINH
Address approval Cleared 8/25/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 8/28/2023 NIKKI ZULUETA
Sewer availability Cleared 8/29/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 9/16/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/9/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 4/16/2024 BRYAN GODINEZ
Hold Cleared 6/10/2024 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Dia,, Gil Aroja; Lic. No.: C26172 532 E 222ND STREET      CARSON, CA 90745

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/11/2024 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 6/11/2024 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 6/11/2024 Approved MICHEL ABAJAN
METHANE-Subgrade 6/11/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 6/11/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/1/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 7/3/2024 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/1/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Inspection MICHEL ABAJAN
Interior/Exterior Lathing 11/4/2024 Approved MICHEL ABAJAN
Sewer 11/4/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 1/21/2025 Corrections Issued MICHEL ABAJAN
METHANE-Rough 1/21/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 1/21/2025 Corrections Issued MICHEL ABAJAN
Verify Sprinkler Sign Off 1/21/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/5/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/5/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 3/5/2025 Approved MICHEL ABAJAN
Insulation 3/27/2025 Conditional Approval MICHEL ABAJAN
Drywall Nailing 4/29/2025 Approved LOUIS ESCOTO
Insulation 4/29/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 4/29/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 9/5/2025 Approved MICHEL ABAJAN
Final 9/5/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 9/5/2025 Approved MICHEL ABAJAN
PLUMBING-Final 9/5/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 9/5/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 9/5/2025 Approved MICHEL ABAJAN