11245 N NORRIS AVE 91331
Certificate Information: 11245 N NORRIS AVE 91331
- Application / Permit
- 22010-20000-06703
- Plan Check / Job No.
- B22VN19193
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New detached 738 sq ft ADU.Per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 ofLAMC 12.22 A.33(c)-(d), (g)
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- Issued on 4/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | ALFREDO JARA |
| Corrections Issued | 1/28/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 4/5/2024 | ALFREDO JARA |
| Plan Check Approved | 4/21/2024 | ALFREDO JARA |
| Issued | 4/22/2024 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/12/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/12/2023 | RIDWAN HARDY |
| Clean Up Green Up | Cleared | 8/17/2023 | KENTON TRINH |
| ZI | Cleared | 8/17/2023 | KENTON TRINH |
| Address approval | Cleared | 8/25/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 8/29/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 9/16/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 2/9/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/16/2024 | BRYAN GODINEZ |
| Hold | Cleared | 6/10/2024 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dia,, Gil Aroja; Lic. No.: C26172 | 532 E 222ND STREET CARSON, CA 90745 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/11/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 6/11/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 6/11/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/11/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/3/2024 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/4/2024 | Approved | MICHEL ABAJAN |
| Sewer | 11/4/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/21/2025 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Rough | 1/21/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/21/2025 | Corrections Issued | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 1/21/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/5/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/5/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/5/2025 | Approved | MICHEL ABAJAN |
| Insulation | 3/27/2025 | Conditional Approval | MICHEL ABAJAN |
| Drywall Nailing | 4/29/2025 | Approved | LOUIS ESCOTO |
| Insulation | 4/29/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 4/29/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 9/5/2025 | Approved | MICHEL ABAJAN |
| Final | 9/5/2025 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 9/5/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/5/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 9/5/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 9/5/2025 | Approved | MICHEL ABAJAN |