6245 N MCLAREN AVE 91367

Certificate Information: 6245 N MCLAREN AVE 91367

Application / Permit
22010-20000-06694
Plan Check / Job No.
B22VN19190
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-Story Detached ADU per LAMC 12.22A.33 (c) and (d)
Permit Issued
Issued on 4/28/2023
Issuing Office
Current Status
CofO Issued on 12/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 DAVID CASTILLO
Corrections Issued 1/29/2023 DAVID CASTILLO
Applicant returned to address corrections 4/20/2023 DAVID CASTILLO
Applicant returned to address corrections 4/26/2023 JOE VO
Plan Check Approved 4/28/2023 JOE VO
Issued 4/28/2023 APPLICANT
CofO in Progress 10/31/2025 TROY SANDERS
Permit Finaled 12/5/2025 MICHAEL PELHAM
CofO Issued 12/5/2025 MICHAEL PELHAM
Permit Finaled 12/5/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 1/31/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/31/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/1/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 2/1/2023 DAGOVERTO GUERRERO
Stormwater Pollution Mitigatn Cleared 3/7/2023 ANTHONY VARGAS
Grading Pre-Inspection Cleared 4/20/2023 DAVID CASTILLO

Contact Information

Contractor Aram G Construction Inc; Lic. No.: 961066-B       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/1/2023 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 5/23/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval TROY SANDERS
ELECTRICAL-Rough 9/18/2023 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 9/18/2023 Approved MORRIS JACKSON
Shower Pan 9/18/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 9/25/2023 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval TROY SANDERS
HVAC-Rough 9/25/2023 Approved TROY SANDERS
Underground Mechanical 9/25/2023 Approved TROY SANDERS
Insulation 10/30/2023 Approved TROY SANDERS
Interior/Exterior Lathing 10/30/2023 Partial Approval TROY SANDERS
Drywall Nailing 11/28/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/28/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 10/29/2024 Approved TROY SANDERS
Final 10/29/2024 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 10/29/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved TROY SANDERS
Service/Power Release 10/29/2024 Not Ready for Inspection TROY SANDERS
Smoke Detectors 10/29/2024 Approved TROY SANDERS
Verify Sprinkler Sign Off 10/29/2024 Approved TROY SANDERS
Service/Power Release 12/10/2024 Approved TROY SANDERS
Final 3/5/2025 Corrections Issued TROY SANDERS
Final 10/30/2025 OK to Issue CofO TROY SANDERS