6245 N MCLAREN AVE 91367
Certificate Information: 6245 N MCLAREN AVE 91367
- Application / Permit
- 22010-20000-06694
- Plan Check / Job No.
- B22VN19190
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-Story Detached ADU per LAMC 12.22A.33 (c) and (d)
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Current Status
- CofO Issued on 12/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | DAVID CASTILLO |
| Corrections Issued | 1/29/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/20/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/26/2023 | JOE VO |
| Plan Check Approved | 4/28/2023 | JOE VO |
| Issued | 4/28/2023 | APPLICANT |
| CofO in Progress | 10/31/2025 | TROY SANDERS |
| Permit Finaled | 12/5/2025 | MICHAEL PELHAM |
| CofO Issued | 12/5/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/5/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/1/2023 | DAGOVERTO GUERRERO |
| Stormwater Pollution Mitigatn | Cleared | 3/7/2023 | ANTHONY VARGAS |
| Grading Pre-Inspection | Cleared | 4/20/2023 | DAVID CASTILLO |
Contact Information
| Contractor | Aram G Construction Inc; Lic. No.: 961066-B | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/1/2023 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 9/18/2023 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 9/18/2023 | Approved | MORRIS JACKSON |
| Shower Pan | 9/18/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/25/2023 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Partial Approval | TROY SANDERS |
| HVAC-Rough | 9/25/2023 | Approved | TROY SANDERS |
| Underground Mechanical | 9/25/2023 | Approved | TROY SANDERS |
| Insulation | 10/30/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/30/2023 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 11/28/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/28/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | TROY SANDERS |
| Final | 10/29/2024 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 10/29/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 10/29/2024 | Not Ready for Inspection | TROY SANDERS |
| Smoke Detectors | 10/29/2024 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 10/29/2024 | Approved | TROY SANDERS |
| Service/Power Release | 12/10/2024 | Approved | TROY SANDERS |
| Final | 3/5/2025 | Corrections Issued | TROY SANDERS |
| Final | 10/30/2025 | OK to Issue CofO | TROY SANDERS |