1220 N CORSICA DR 90272

Certificate Information: 1220 N CORSICA DR 90272

Application / Permit
22010-20000-06648
Plan Check / Job No.
B22VN19173
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 83'-9" X 68'-2" TWO STORY SINGLE FAMILY DWELLING WITH BASEMENT ATTACHED TRELLIS AND THREE CAR GARAGE ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 6/30/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 2/21/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 2/22/2023 OMID HEDAYAT
Building Plans Picked Up 2/28/2023 APPLICANT
Applicant returned to address corrections 4/5/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/20/2023 SEWADA ZADOORAN MILAGARDI
Issued 6/30/2023 APPLICANT
CofO in Progress 3/6/2026 HERBERT GIRON
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
Permit Cleared 2/23/2023 ANTHONY MAINEZ
Sewer availability Cleared 2/23/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/27/2023 ANTHONY MAINEZ
Trees in Parkway Cleared 3/22/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 3/24/2023 MATTHEW CRAIG
Stormwater Pollution Mitigatn Cleared 4/10/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/19/2023 ANTHONY MAINEZ
Excavation more than 5-ft deep Cleared 4/20/2023 CALOSHA APPROVED
GPI Written Notices Cleared 4/20/2023 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 4/20/2023 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Sky Remodeling Inc; Lic. No.: 955109-B 12439 MAGNOLIA BLVD #245      VALLEY VILLAGE, CA 91607
Engineer Danz,, Joshua; Lic. No.: C84764 1164 ELDERBERRY CIRCLE      FOLSOM, CA 95630
Engineer Tani,, Jason; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 9/29/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 10/17/2023 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 10/19/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/3/2023 Partial Approval KEVIN SARGSYAN
Reinforced Concrete Frame 11/3/2023 Partial Approval KEVIN SARGSYAN
Deputy Shotcrete 11/6/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Shotcrete 11/7/2023 Partial Approval OGANES TARAKHCHYAN
Special/Order Compliance 11/28/2023 Not Ready for Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 12/14/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 1/8/2024 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 1/9/2024 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval KENNETH NAGLE
Deputy Steel/Welding 1/29/2024 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/21/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 3/21/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 3/21/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 3/22/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval CARLOS MATAMOROS
HVAC-Rough 3/22/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/22/2024 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 4/8/2024 Approved ARAM AVEDISIAN
Green Building Rough 4/8/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/8/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/8/2024 Approved ARAM AVEDISIAN
Shower Pan 4/8/2024 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 4/8/2024 Approved ARAM AVEDISIAN
Insulation 4/12/2024 Approved KEVIN SARGSYAN
Drywall Nailing 4/25/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/7/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 3/19/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 4/3/2025 Corrections Issued HERBERT GIRON
HVAC-Final 4/3/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 4/3/2025 Corrections Issued HERBERT GIRON
HVAC-Final 4/16/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 4/16/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/19/2025 Corrections Issued HERBERT GIRON
Gas Test 9/19/2025 Approved HERBERT GIRON
HVAC-Final 9/19/2025 Partial Approval HERBERT GIRON
PLUMBING-Final 9/19/2025 Approved HERBERT GIRON
ELECTRICAL-Final 10/3/2025 Not Ready for Inspection HERBERT GIRON
Final 10/3/2025 Not Ready for Inspection HERBERT GIRON
Green Building Final 10/3/2025 Approved HERBERT GIRON
HVAC-Final 10/3/2025 Not Ready for Inspection HERBERT GIRON
Reinforced Concrete Frame 10/3/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Approved HERBERT GIRON
Smoke Detectors 10/3/2025 Approved HERBERT GIRON
ELECTRICAL-Final 10/20/2025 Partial Approval HERBERT GIRON
ELECTRICAL-Final 1/26/2026 Approved HERBERT GIRON
Final 1/26/2026 Corrections Issued HERBERT GIRON
HVAC-Final 1/26/2026 Approved HERBERT GIRON
Service/Power Release 1/29/2026 Approved JUAN VALENZUELA
Final 2/27/2026 Corrections Issued HERBERT GIRON
Final 3/5/2026 OK to Issue CofO HERBERT GIRON