6752-6756 N BEN AVE 91605

Certificate Information: 6752-6756 N BEN AVE 91605

Application / Permit
22010-20000-06632
Plan Check / Job No.
B22VN19160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 43'-4" x 38' THREE STORY DUPLEX W/ ATT. ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c) and (e)] AND 2 ONE-CAR GARAGES; NFPA-13D THRU-OUT
Permit Issued
Issued on 10/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 RAMA DABADGE
Corrections Issued 2/15/2023 RAMA DABADGE
Disabled Access Plans Picked Up 2/23/2023 APPLICANT
Quality Review Completed 2/24/2023 STEVEN KIM
Building Plans Picked Up 2/28/2023 APPLICANT
Applicant returned to address corrections 7/26/2023 RAMA DABADGE
Applicant returned to address corrections 9/25/2023 SEAN SHAHMIRI
Plan Check Approved 10/5/2023 SEAN SHAHMIRI
Issued 10/6/2023 APPLICANT
CofO in Progress 11/14/2025 RAUL OLAGI
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/22/2023 DAGOVERTO GUERRERO
Address approval Cleared 3/23/2023 DAGOVERTO GUERRERO
Highway dedication Cleared 4/7/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 5/10/2023 RIDWAN HARDY
Stormwater Pollution Mitigatn Cleared 6/20/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/12/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 7/13/2023 DAGOVERTO GUERRERO
ZA Case Cleared 7/28/2023 DALIA MOKAYED
ZA Case Cleared 7/28/2023 DALIA MOKAYED
ZA Case Cleared 7/28/2023 DALIA MOKAYED
Trees in Parkway Cleared 8/2/2023 ADALBERTO VERA
DAS Clearance Cleared 8/9/2023 RAMA DABADGE
Hydrant and Access approval Cleared 8/21/2023 GILBERT URREA
Permit Cleared 9/18/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Golden Point Construction; Lic. No.: 965193-B 731 EAST 75TH STREET      LOS ANGELES, CA 90001
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2023 No Access for Inspection DAVID MATSON
Underground Mechanical 12/6/2023 No Access for Inspection DAVID MATSON
HVAC-Rough 1/4/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/4/2024 Not Ready for Inspection JOHN HAYES
Underground Mechanical 1/4/2024 Corrections Issued JOHN HAYES
PLUMBING-Rough 1/9/2024 Partial Approval JOHN HAYES
Underground Mechanical 1/9/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 1/29/2024 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 No Access for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued JOSE AVILA
HVAC-Rough 9/4/2024 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 9/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 9/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 9/25/2024 Approved JOSE AVILA
HVAC-Rough 9/25/2024 Approved JOSE AVILA
PLUMBING-Rough 9/25/2024 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 10/3/2024 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 10/3/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 10/9/2024 Not Ready for Inspection JOSE AVILA
Green Building Rough 10/9/2024 Not Ready for Inspection JOSE AVILA
Verify Sprinkler Sign Off 10/9/2024 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 10/25/2024 Corrections Issued JOSE AVILA
Green Building Rough 10/25/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 11/7/2024 Approved JOSE AVILA
Verify Sprinkler Sign Off 11/7/2024 Approved JOSE AVILA
Drywall Nailing 11/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 12/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 12/6/2024 Approved JOSE AVILA
Insulation 12/6/2024 Approved JOSE AVILA
ELECTRICAL-Final 6/9/2025 Corrections Issued JOSE AVILA
HVAC-Final 6/9/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 6/9/2025 Conditional Approval JOSE AVILA
ELECTRICAL-Final 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Final 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/24/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/18/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/18/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/18/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/28/2025 Partial Approval JOSE AVILA
HVAC-Final 7/28/2025 Approved JOSE AVILA
PLUMBING-Final 7/28/2025 Partial Approval JOSE AVILA
Final 9/26/2025 Corrections Issued JOSE AVILA
Green Building Final 9/26/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 9/26/2025 Approved JOSE AVILA
Final 10/9/2025 Corrections Issued JOSE AVILA
Service/Power Release 10/9/2025 Approved JOSE AVILA
Final 11/14/2025 OK to Issue CofO JOSE AVILA