11950-11952 W VANOWEN ST 91605
Certificate Information: 11950-11952 W VANOWEN ST 91605
- Application / Permit
- 22010-20000-06555
- Plan Check / Job No.
- B22VN19047
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT; NO PARKING REQ'D PER AB2097
- Permit Issued
- Issued on 10/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | SELLA BENYAMIN |
| Corrections Issued | 2/7/2023 | SELLA BENYAMIN |
| Quality Review Completed | 2/10/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/10/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 2/16/2023 | APPLICANT |
| Plan Check Approved | 8/31/2023 | SELLA BENYAMIN |
| Issued | 10/5/2023 | APPLICANT |
| CofO in Progress | 11/14/2025 | RAUL OLAGI |
| No Progress | 2/13/2026 | JOSE AVILA |
| CofO in Progress | 2/13/2026 | JOSE AVILA |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
| CofO Issued | 2/17/2026 | RUBEN SALAS |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | DAGOVERTO GUERRERO |
| Stormwater Pollution Mitigatn | Cleared | 6/21/2023 | ANTHONY VARGAS |
| Highway dedication | Cleared | 6/27/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 7/6/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/12/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/13/2023 | DAGOVERTO GUERRERO |
| DAS Clearance | Cleared | 8/9/2023 | SELLA BENYAMIN |
| Hydrant and Access approval | Cleared | 8/18/2023 | GILBERT URREA |
Contact Information
| Contractor | Golden Point Construction; Lic. No.: 965193-B | 731 EAST 75TH STREET LOS ANGELES, CA 90001 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/11/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 1/11/2024 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 1/11/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/17/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 1/17/2024 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 2/12/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 6/28/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Not Ready for Inspection | JOSE AVILA |
| Deputy Wood Construction | 7/30/2024 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/22/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/26/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/26/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/26/2024 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 9/4/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 9/12/2024 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 9/12/2024 | Approved | JOSE AVILA |
| Insulation | 9/12/2024 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/24/2024 | Approved | JOSE AVILA |
| Insulation | 9/24/2024 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 10/30/2024 | Partial Approval | JOSE AVILA |
| Service/Power Release | 4/9/2025 | Partial Inspection | JOSE AVILA |
| HVAC-Final | 5/29/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 5/29/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/4/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 6/24/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 6/24/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/30/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 6/30/2025 | Approved | JOSE AVILA |
| Final | 10/23/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 10/23/2025 | Approved | JOSE AVILA |
| Service/Power Release | 10/23/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 10/23/2025 | Approved | JOSE AVILA |
| Final | 11/14/2025 | OK to Issue CofO | JOSE AVILA |
| Special/Order Compliance | 2/12/2026 | Approved | ROBERTO PALACIOS-LOPEZ |