20409 W EDGEWOOD CT 91311

Certificate Information: 20409 W EDGEWOOD CT 91311

Application / Permit
22010-20000-06516
Plan Check / Job No.
B22VN19001
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED GARAGE (STANDARD PLAN 656 _ PLAN 1D) _ BUILDING SHALL BE FULLY SPRINKLER WITH NFPA 13D.
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
CofO Issued on 3/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 PETER MOSESIAN
Corrections Issued 2/22/2023 DAWN MC NULTY
Quality Review Completed 2/23/2023 STEVEN KIM
Building Plans Picked Up 2/23/2023 APPLICANT
Applicant returned to address corrections 9/14/2023 DAWN MC NULTY
Applicant returned to address corrections 9/18/2023 DAWN MC NULTY
Applicant returned to address corrections 10/31/2023 DAWN MC NULTY
Applicant returned to address corrections 11/1/2023 DAWN MC NULTY
Applicant returned to address corrections 11/3/2023 DAWN MC NULTY
Applicant returned to address corrections 12/21/2023 DAWN MC NULTY
Plan Check Approved 6/9/2024 DAWN MC NULTY
Issued 6/24/2024 APPLICANT
CofO in Progress 3/21/2025 JEFFREY PARD
Permit Finaled 3/25/2025 JOHN JANSON
CofO Issued 3/25/2025 JOHN JANSON
Permit Finaled 3/25/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/26/2023 LEE GUILBEAUX
Permit Cleared 7/26/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/26/2023 DAWN MC NULTY
Roof/Waste drainage to street Cleared 7/26/2023 LEE GUILBEAUX
Sewer availability Cleared 7/26/2023 LEE GUILBEAUX
Low Impact Development Cleared 9/18/2023 MARTIN FRAGOSO
"T" removal Cleared 10/5/2023 BRENNEN OBETO
CPC Cleared 10/5/2023 BRENNEN OBETO
Miscellaneous Cleared 10/5/2023 BRENNEN OBETO
Private street Cleared 10/5/2023 BRENNEN OBETO
Tract Map conditions Cleared 10/5/2023 BRENNEN OBETO
ZA Case Cleared 10/5/2023 BRENNEN OBETO
Miscellaneous Cleared 10/7/2023 BRENNEN OBETO
GPI Written Notices Cleared 11/5/2023 DAWN MC NULTY
Grading Pre-Inspection Cleared 11/5/2023 DAWN MC NULTY
Miscellaneous Cleared 11/5/2023 DAWN MC NULTY
Specific Plan Cleared 1/5/2024 BRENNEN OBETO
Miscellaneous Cleared 1/15/2024 STEVEN WECHSLER
Hydrant and Access approval Cleared 5/16/2024 MATTHEW CRAIG
Drainage to Storm Drain Cleared 6/11/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/11/2024 CARLOS AGUILERA

Contact Information

Architect Swift,, Daniel R; Lic. No.: C32860 4601 WESTOWN PARKWAY SUITE 208      WEST DES MOINES, IA 50266
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Braatz,, Tara Elizabeth; Lic. No.: C79028 24855 CALLE CARMEL      LAGUNA HILLS, CA 92653
Engineer Toedter,, Randy W; Lic. No.: S2991 689 COUNTY SQUARE DR UNIT 32      VENTURA, CA 93003
Engineer Van, Gaale, Mark Allan; Lic. No.: C58680 185 W ORANGEWOOD AVE STE 200      ORANGE, CA 92868

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/27/2024 Partial Approval JEFFREY PARD
Sewer 6/27/2024 Approved JEFFREY PARD
Deputy Pre-Stress Concrete 7/17/2024 Approved JEFFREY PARD
Footing/Foundation/Slab 7/18/2024 Approved JEFFREY PARD
Deputy Reinf. Concrete 7/19/2024 Approved JEFFREY PARD
Deputy Pre-Stress Concrete 7/25/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved JEFFREY PARD
Deputy Drilled-In Anchors 8/23/2024 Approved JEFFREY PARD
Deputy Wood Construction 8/23/2024 Approved JEFFREY PARD
ELECTRICAL-Rough 9/6/2024 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 9/6/2024 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 9/12/2024 Approved JEFFREY PARD
HVAC-Rough 9/12/2024 Approved JEFFREY PARD
ELECTRICAL-Rough 9/18/2024 Approved JEFFREY PARD
HVAC-Rough 9/18/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 9/19/2024 Approved JEFFREY PARD
PLUMBING-Rough 9/19/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/25/2024 Approved JEFFREY PARD
Green Building Rough 9/25/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 9/25/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 9/27/2024 Not Ready for Inspection JEFFREY PARD
Insulation 10/1/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 10/1/2024 Approved JEFFREY PARD
Drywall Nailing 10/15/2024 Approved JEFFREY PARD
Underground Mechanical 11/7/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 11/8/2024 Approved JEFFREY PARD
Gas Test 11/14/2024 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved HENRY KIM
Service/Power Release 12/10/2024 Approved JEFFREY PARD
ELECTRICAL-Final 12/31/2024 Approved JEFFREY PARD
HVAC-Final 12/31/2024 Approved JEFFREY PARD
PLUMBING-Final 12/31/2024 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 1/8/2025 Approved JEFFREY PARD
Final 1/10/2025 Not Ready for Inspection JEFFREY PARD
Green Building Final 1/10/2025 Approved JEFFREY PARD
Smoke Detectors 1/10/2025 Approved JEFFREY PARD
Final 3/20/2025 OK to Issue CofO JEFFREY PARD