4956 N BILOXI AVE 91601
Certificate Information: 4956 N BILOXI AVE 91601
- Application / Permit
- 22010-20000-06476
- Plan Check / Job No.
- B22VN18960
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan SB9 URBAN LOT SPLIT: #1 Bldg-Addition: REMODEL AND ADDITION TO (E) 1-STORY 'SFD 1' W/ PROPOSED 2ND STORY. ATTACHED 'ADU 1' WITH AN SB9 URBAN SPLIT CA GOVT CODE 66411.7 (REDUCED SCOPE OF WORK PER 22010-20001-06476: REMOVE ADU 'A' ATTACHED TO (E) SFD 'A' AND REMOVE SB9 LOT SPLIT FROM THE SCOPE OF WORK) ADU CHECKED PER LAMC 12.22 A.33(C) AND (E) LID clearance has been deferred
- Permit Issued
- Issued on 11/14/2024
- Issuing Office
- Current Status
- Issued on 11/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | SUNMIN LEE |
| Corrections Issued | 2/9/2023 | SUNMIN LEE |
| Quality Review Completed | 2/23/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/2/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 6/14/2023 | SUNMIN LEE |
| Plan Check Approved | 8/2/2024 | SUNMIN LEE |
| Issued | 11/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/14/2023 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/15/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 5/8/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/8/2024 | CARLOS AGUILERA |
Contact Information
| Architect | Beauter,, William L; Lic. No.: C29188 | 2664 LACY STREET STUDIO A LOS ANGELES, CA 90031 |
| Architect | Beauter,, William L; Lic. No.: NA29188 | , |
| Contractor | Cali Builders & Construction Inc; Lic. No.: 1051566-B | , |
| Engineer | Soliman,, Magdi G; Lic. No.: L8822 | 19246 BENSION DR SANTA CLARITA, CA 91350 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 |
| Insulation | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 11/18/2024 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 11/21/2024 | Approved | JOSE AVILA |
| Pre-Inspection | 2/20/2025 | Corrections Issued | JUAN VALENZUELA |
| Underground Mechanical | 2/9/2026 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 3/16/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/7/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/14/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 4/21/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/29/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2026 | No Result Entered | ROBERTO PALACIOS-LOPEZ |