16102 W CALAHAN ST 91343

Certificate Information: 16102 W CALAHAN ST 91343

Application / Permit
22010-20000-06470
Plan Check / Job No.
B22VN18957
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New detached ADU per PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/4/2023
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/3/2023 HANS SANTIAGO
Corrections Issued 1/4/2023 HANS SANTIAGO
Plan Check Approved 8/2/2023 ANDREW SANTIAGO
Issued 9/4/2023 APPLICANT
CofO in Progress 5/17/2024 RAUL OLAGI
Permit Finaled 5/29/2024 RUBEN SALAS
Permit Finaled 5/29/2024 RUBEN SALAS
CofO Issued 5/29/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/11/2023 DAGOVERTO GUERRERO
Miscellaneous Cleared 1/11/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/12/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/12/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 2/4/2023 KURT CORRAL
Construction near power lines Cleared 4/28/2023 RIDWAN HARDY
Construction near power lines Cleared 4/28/2023 RIDWAN HARDY
Construction within easement Cleared 4/28/2023 RIDWAN HARDY
Low Impact Development Cleared 7/13/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 7/31/2023 TAL SHEMEN
GPI Written Notices Cleared 8/2/2023 ANDREW SANTIAGO
Grading Pre-Inspection Cleared 8/2/2023 ANDREW SANTIAGO

Contact Information

Contractor Sharp Builders & Son; Lic. No.: 1058253-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 10/23/2023 Not Ready for Inspection RAUL OLAGI
Sewer 10/23/2023 Approved RAUL OLAGI
Underground Mechanical 10/23/2023 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/30/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 10/30/2023 Approved RAUL OLAGI
PLUMBING-Rough 10/30/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 12/11/2023 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 12/20/2023 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/26/2023 Partial Approval RAUL OLAGI
HVAC-Rough 12/26/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 12/26/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 1/3/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 1/3/2024 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 1/3/2024 Approved RAUL OLAGI
Verify Sprinkler Sign Off 1/3/2024 Approved RAUL OLAGI
Insulation 1/4/2024 Approved RAUL OLAGI
Drywall Nailing 1/9/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 1/17/2024 Approved RAUL OLAGI
Shower Pan 1/17/2024 Approved RAUL OLAGI
Final 5/15/2024 Corrections Issued RAUL OLAGI
Green Building Final 5/15/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/15/2024 Approved RAUL OLAGI
Final 5/17/2024 OK to Issue CofO RAUL OLAGI
Service/Power Release 5/17/2024 Approved RAUL OLAGI