16102 W CALAHAN ST 91343
Certificate Information: 16102 W CALAHAN ST 91343
- Application / Permit
- 22010-20000-06470
- Plan Check / Job No.
- B22VN18957
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New detached ADU per PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/4/2023
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | HANS SANTIAGO |
| Corrections Issued | 1/4/2023 | HANS SANTIAGO |
| Plan Check Approved | 8/2/2023 | ANDREW SANTIAGO |
| Issued | 9/4/2023 | APPLICANT |
| CofO in Progress | 5/17/2024 | RAUL OLAGI |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
| CofO Issued | 5/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2023 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 1/11/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 2/4/2023 | KURT CORRAL |
| Construction near power lines | Cleared | 4/28/2023 | RIDWAN HARDY |
| Construction near power lines | Cleared | 4/28/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/28/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/13/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 7/31/2023 | TAL SHEMEN |
| GPI Written Notices | Cleared | 8/2/2023 | ANDREW SANTIAGO |
| Grading Pre-Inspection | Cleared | 8/2/2023 | ANDREW SANTIAGO |
Contact Information
| Contractor | Sharp Builders & Son; Lic. No.: 1058253-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/13/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 10/23/2023 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 10/23/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 10/23/2023 | Approved | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 10/30/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 12/11/2023 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 12/20/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/26/2023 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 12/26/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 12/26/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/3/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 1/3/2024 | Partial Approval | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 1/3/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 1/3/2024 | Approved | RAUL OLAGI |
| Insulation | 1/4/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 1/9/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 1/17/2024 | Approved | RAUL OLAGI |
| Shower Pan | 1/17/2024 | Approved | RAUL OLAGI |
| Final | 5/15/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/15/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/15/2024 | Approved | RAUL OLAGI |
| Final | 5/17/2024 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 5/17/2024 | Approved | RAUL OLAGI |