6920 N KATHERINE AVE 91405
Certificate Information: 6920 N KATHERINE AVE 91405
- Application / Permit
- 22010-20000-06462
- Plan Check / Job No.
- B22VN18934
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. NEW DETACHED 1-STORY ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- Current Status
- CofO Issued on 12/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | MINA HABILI |
| Corrections Issued | 1/27/2023 | MINA HABILI |
| Applicant returned to address corrections | 4/28/2023 | KEVIN MORALES |
| Plan Check Approved | 5/3/2023 | KEVIN MORALES |
| Issued | 10/30/2023 | APPLICANT |
| CofO in Progress | 12/11/2024 | RYAN SALAZAR |
| Permit Finaled | 12/15/2024 | RUBEN SALAS |
| CofO Issued | 12/15/2024 | RUBEN SALAS |
| Permit Finaled | 12/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/9/2023 | DAGOVERTO GUERRERO |
| Hold | Cleared | 4/25/2023 | MARIA VENDIVIL |
| Stormwater Pollution Mitigatn | Cleared | 4/26/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 4/27/2023 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Calabia,, Carlito Serrano; Lic. No.: C25200 | 6922 KATHERINE AVENUE VAN NUYS, CA 91405 |
| Contractor | Owner-Builder | , |
| Engineer | Onishi,, Robert K; Lic. No.: S3705 | 4438 LINDBLADE DRIVE LOS ANGELES, CA 90066 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/7/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 12/19/2023 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/19/2023 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 1/17/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 1/17/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/24/2024 | Approved | RYAN SALAZAR |
| Sewer | 1/24/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 2/12/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/28/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/28/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 2/28/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/7/2024 | Corrections Issued | RYAN SALAZAR |
| HVAC-Rough | 3/7/2024 | Approved | RYAN SALAZAR |
| Insulation | 3/13/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/18/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/22/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 6/6/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 8/5/2024 | Partial Approval | RYAN SALAZAR |
| Final | 8/5/2024 | Corrections Issued | RYAN SALAZAR |
| HVAC-Final | 8/5/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 8/5/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | RYAN SALAZAR |
| Final | 12/6/2024 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 12/6/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/6/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 12/6/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 12/6/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/6/2024 | Approved | RYAN SALAZAR |
| Final | 12/11/2024 | OK to Issue CofO | RYAN SALAZAR |