734-734 1/2 E 83RD ST 90001
Certificate Information: 734-734 1/2 E 83RD ST 90001
- Application / Permit
- 22010-20000-06443
- Plan Check / Job No.
- B22VN18893
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY (25'-0"x94'-0"), 3715 SQFT DUPLEX W/ ATTACHED 2 CAR GARAGE (380 SQFT) AND 1-CAR GARAGE (184 SQFT) AND 37 SQFT COVERED PORCH W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | PETER MOSESIAN |
| Corrections Issued | 1/29/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/31/2023 | OMID HEDAYAT |
| Plan Check Approved | 7/26/2023 | PETER MOSESIAN |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 4/17/2024 | MICHAEL LEWIS |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
| CofO Issued | 4/18/2024 | DEROLD HAUFF |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 3/3/2023 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 3/15/2023 | DANIEL CORONADO |
| Sewer availability | Cleared | 6/12/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 6/21/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 6/25/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 10/20/2023 | Conditional Approval | MICHAEL LEWIS |
| Sewer | 10/30/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 10/30/2023 | Approved | MICHAEL LEWIS |
| Wood Frame | 10/30/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Partial Approval | MICHAEL LEWIS |
| Insulation | 10/31/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 12/1/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 12/14/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 12/14/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 12/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/19/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 1/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/24/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 2/27/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Final | 4/8/2024 | Approved | MICHAEL LEWIS |
| Final | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Gas Test | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 4/8/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 4/8/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 4/8/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 4/8/2024 | Approved | MICHAEL LEWIS |
| Gas Test | 4/11/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 4/11/2024 | Approved | MICHAEL LEWIS |
| Final | 4/16/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 4/16/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 4/16/2024 | Approved | MICHAEL LEWIS |