734-734 1/2 E 83RD ST 90001

Certificate Information: 734-734 1/2 E 83RD ST 90001

Application / Permit
22010-20000-06443
Plan Check / Job No.
B22VN18893
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY (25'-0"x94'-0"), 3715 SQFT DUPLEX W/ ATTACHED 2 CAR GARAGE (380 SQFT) AND 1-CAR GARAGE (184 SQFT) AND 37 SQFT COVERED PORCH W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/26/2023
Issuing Office
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 PETER MOSESIAN
Corrections Issued 1/29/2023 PETER MOSESIAN
Quality Review Completed 1/31/2023 OMID HEDAYAT
Plan Check Approved 7/26/2023 PETER MOSESIAN
Issued 9/26/2023 APPLICANT
CofO in Progress 4/17/2024 MICHAEL LEWIS
Permit Finaled 4/18/2024 DEROLD HAUFF
CofO Issued 4/18/2024 DEROLD HAUFF
Permit Finaled 4/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/11/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/21/2023 TREVOR QUAN
Hydrant and Access approval Cleared 3/3/2023 MATTHEW CRAIG
Frnt yard landscape/Water mgmt Cleared 3/15/2023 DANIEL CORONADO
Sewer availability Cleared 6/12/2023 TREVOR QUAN
Low Impact Development (LID) Cleared 6/21/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 6/25/2023 AHMED AMARRAGY

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/16/2023 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/16/2023 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 10/20/2023 Conditional Approval MICHAEL LEWIS
Sewer 10/30/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/30/2023 Approved MICHAEL LEWIS
Wood Frame 10/30/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Partial Approval MICHAEL LEWIS
Insulation 10/31/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval JOSEPH MCGARRY
Deputy Wood Construction 12/1/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Approved MICHAEL LEWIS
HVAC-Rough 12/14/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 12/14/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/15/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/15/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 12/15/2023 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/15/2023 Approved ALEJANDRO DE ARTOLA
Insulation 12/19/2023 Approved MICHAEL LEWIS
Drywall Nailing 1/2/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/2/2024 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/24/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/27/2024 Partial Approval MICHAEL LEWIS
ELECTRICAL-Final 4/8/2024 Approved MICHAEL LEWIS
Final 4/8/2024 Corrections Issued MICHAEL LEWIS
Gas Test 4/8/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 4/8/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 4/8/2024 Approved MICHAEL LEWIS
PLUMBING-Final 4/8/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 4/8/2024 Approved MICHAEL LEWIS
Smoke Detectors 4/8/2024 Approved MICHAEL LEWIS
Gas Test 4/11/2024 Approved MICHAEL LEWIS
PLUMBING-Final 4/11/2024 Approved MICHAEL LEWIS
Final 4/16/2024 OK to Issue CofO MICHAEL LEWIS
Green Building Final 4/16/2024 Approved MICHAEL LEWIS
Service/Power Release 4/16/2024 Approved MICHAEL LEWIS