231-233 W 74TH ST 90003

Certificate Information: 231-233 W 74TH ST 90003

Application / Permit
22010-20000-06442
Plan Check / Job No.
B22VN18892
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan; PROPOSED 2-STORY DUPLEX WITH AN ATTACHED 3-CAR GARAGE.
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2023 APPLICANT
Assigned to Plan Check Engineer 1/25/2023 MICHAEL LOPEZ
Corrections Issued 2/2/2023 MICHAEL LOPEZ
Quality Review Completed 2/10/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/7/2023 MICHAEL LOPEZ
Plan Check Approved 4/25/2023 MICHAEL LOPEZ
Issued 7/26/2023 APPLICANT
CofO in Progress 2/8/2024 MICHAEL LEWIS
CofO Issued 2/12/2024 DEROLD HAUFF
Permit Finaled 2/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/23/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/2/2023 CINDY QI
Sewer availability Cleared 3/2/2023 CINDY QI
Hydrant and Access approval Cleared 3/10/2023 GILBERT URREA
Low Impact Development Cleared 3/16/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 3/21/2023 CINDY QI

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/11/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 8/17/2023 Partial Approval MICHAEL LEWIS
Wood Frame 8/17/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval MICHAEL LEWIS
Insulation 8/18/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 9/12/2023 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Approved MICHAEL LEWIS
HVAC-Rough 10/4/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 10/4/2023 Approved MICHAEL LEWIS
Sewer 10/4/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/5/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 10/5/2023 Approved MICHAEL LEWIS
Green Building Rough 10/5/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 10/5/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/11/2023 Approved MICHAEL LEWIS
Insulation 10/11/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/23/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/23/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/2/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/4/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 1/31/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 1/31/2024 Approved MICHAEL LEWIS
Service/Power Release 1/31/2024 Corrections Issued MICHAEL LEWIS
Final 2/1/2024 Corrections Issued MICHAEL LEWIS
Gas Test 2/1/2024 Approved MICHAEL LEWIS
Green Building Final 2/1/2024 Approved MICHAEL LEWIS
PLUMBING-Final 2/1/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 2/1/2024 Approved MICHAEL LEWIS
Smoke Detectors 2/1/2024 Approved MICHAEL LEWIS
Final 2/7/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 2/7/2024 Approved MICHAEL LEWIS