10004 N PINEWOOD AVE 91042
Certificate Information: 10004 N PINEWOOD AVE 91042
- Application / Permit
- 22010-20000-06405
- Plan Check / Job No.
- B22VN18835
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Current Status
- Issued on 3/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2022 | DANIEL YIP |
| Corrections Issued | 12/30/2022 | DANIEL YIP |
| Applicant returned to address corrections | 1/23/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/31/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/22/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/4/2023 | MOHAMMAD ESMAILI |
| Issued | 3/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/5/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 1/19/2023 | KIRK LINKLATER |
| ZI | Cleared | 1/20/2023 | SARAH HOUNSELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 4/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 4/20/2023 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/27/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/31/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 5/31/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 5/31/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 5/31/2023 | Approved | WILLIAM WREN |
| Sewer | 5/31/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 5/31/2023 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 5/31/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 6/8/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/22/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 6/22/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 6/22/2023 | Approved | WILLIAM WREN |
| Insulation | 6/22/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/22/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Approved | WILLIAM WREN |
| Insulation | 6/28/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 1/2/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/2/2024 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/2/2024 | Approved | MATTHEW NELSON |