1309 N DOHENY DR 90069

Certificate Information: 1309 N DOHENY DR 90069

Application / Permit
22010-20000-06403
Plan Check / Job No.
B22VN18833
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ( 41'-0"x21'-10"), 818 SQFT 1 STORY ACCESSORY DWELLING UNIT W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 PETER MOSESIAN
Corrections Issued 1/16/2023 PETER MOSESIAN
Quality Review Completed 1/19/2023 OMID HEDAYAT
Building Plans Picked Up 1/20/2023 APPLICANT
Plan Check Approved 8/9/2023 PETER MOSESIAN
Issued 8/9/2023 APPLICANT
CofO in Progress 7/17/2025 RAUL BARAJAS
Permit Finaled 7/20/2025 DEROLD HAUFF
CofO Issued 7/20/2025 DEROLD HAUFF
Permit Finaled 7/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/31/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/31/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/31/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/31/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 1/31/2023 AMAAN MALIK
Street Frontage Cleared 1/31/2023 AMAAN MALIK
Hold Cleared 3/22/2023 MARIA VENDIVIL
Low Impact Development Cleared 4/11/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 4/11/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/13/2023 TREVOR QUAN
Sewer availability Cleared 4/13/2023 TREVOR QUAN
Hydrant and Access approval Cleared 4/18/2023 KURT CORRAL
BHO/Hillside ordinance Cleared 7/26/2023 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2023 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 10/2/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 10/11/2023 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Partial Approval RAUL BARAJAS
Wood Frame 10/30/2023 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 4/11/2024 Corrections Issued RAUL BARAJAS
Shower Pan 4/11/2024 Approved RAUL BARAJAS
HVAC-Rough 4/16/2024 Partial Approval RAUL BARAJAS
Wood Frame 5/7/2024 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 6/7/2024 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 6/12/2024 Corrections Issued RAUL BARAJAS
Green Building Rough 6/12/2024 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 6/12/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 6/20/2024 Not Ready for Inspection RAUL BARAJAS
Insulation 6/28/2024 Not Ready for Inspection RAUL BARAJAS
Wood Frame 7/1/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 7/3/2024 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 7/3/2024 Partial Inspection RAUL BARAJAS
Insulation 7/3/2024 Not Ready for Inspection RAUL BARAJAS
Shower Pan 7/3/2024 Approved RAUL BARAJAS
BUILDING-Rough-Frame 7/5/2024 Corrections Issued RAUL BARAJAS
Green Building Rough 7/5/2024 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 7/8/2024 Not Ready for Inspection ROY SPAULDING
Green Building Rough 7/8/2024 Not Ready for Inspection ROY SPAULDING
Insulation 7/8/2024 Not Ready for Inspection ROY SPAULDING
Wood Frame 7/9/2024 Approved RAUL BARAJAS
Drywall Nailing 7/19/2024 Corrections Issued RAUL BARAJAS
Green Building Rough 7/19/2024 Approved RAUL BARAJAS
Drywall Nailing 7/26/2024 Approved RAUL BARAJAS
Special/Order Compliance 3/19/2025 Partial Inspection RAUL BARAJAS
ELECTRICAL-Final 3/24/2025 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 3/24/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 4/1/2025 Corrections Issued RAUL BARAJAS
Gas Test 4/1/2025 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 4/1/2025 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 4/1/2025 Not Ready for Inspection RAUL BARAJAS
Gas Test 4/11/2025 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 4/11/2025 Approved RAUL BARAJAS
PLUMBING-Final 4/11/2025 Corrections Issued RAUL BARAJAS
PLUMBING-Final 4/28/2025 Approved BRIAN SULLIVAN
Gas Test 5/6/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Not Ready BRIAN SULLIVAN
BUILDING-Rough-Frame 6/25/2025 Approved ENRIQUE MIRELES
Final 6/25/2025 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 6/25/2025 Approved ENRIQUE MIRELES
Green Building Final 6/25/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 6/25/2025 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 6/25/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/30/2025 Corrections Issued BRENDAN MORELLI
Final 6/30/2025 Not Ready for Inspection BRENDAN MORELLI
Final 7/7/2025 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 7/7/2025 Not Required RAUL BARAJAS
Final 7/10/2025 No Access for Inspection NICHOLAS LOPEZ
Final 7/14/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 7/17/2025 Approved RAUL BARAJAS
Final 7/17/2025 OK to Issue CofO RAUL BARAJAS