1309 N DOHENY DR 90069
Certificate Information: 1309 N DOHENY DR 90069
- Application / Permit
- 22010-20000-06403
- Plan Check / Job No.
- B22VN18833
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ( 41'-0"x21'-10"), 818 SQFT 1 STORY ACCESSORY DWELLING UNIT W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | PETER MOSESIAN |
| Corrections Issued | 1/16/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/19/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 1/20/2023 | APPLICANT |
| Plan Check Approved | 8/9/2023 | PETER MOSESIAN |
| Issued | 8/9/2023 | APPLICANT |
| CofO in Progress | 7/17/2025 | RAUL BARAJAS |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| CofO Issued | 7/20/2025 | DEROLD HAUFF |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | AMAAN MALIK |
| Street Frontage | Cleared | 1/31/2023 | AMAAN MALIK |
| Hold | Cleared | 3/22/2023 | MARIA VENDIVIL |
| Low Impact Development | Cleared | 4/11/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 4/13/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 4/18/2023 | KURT CORRAL |
| BHO/Hillside ordinance | Cleared | 7/26/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2023 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/2/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/11/2023 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 10/30/2023 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/11/2024 | Corrections Issued | RAUL BARAJAS |
| Shower Pan | 4/11/2024 | Approved | RAUL BARAJAS |
| HVAC-Rough | 4/16/2024 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 5/7/2024 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/7/2024 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/12/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 6/12/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/20/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 6/28/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 7/1/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 7/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 7/3/2024 | Partial Inspection | RAUL BARAJAS |
| Insulation | 7/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 7/3/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/5/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 7/5/2024 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/8/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 7/8/2024 | Not Ready for Inspection | ROY SPAULDING |
| Insulation | 7/8/2024 | Not Ready for Inspection | ROY SPAULDING |
| Wood Frame | 7/9/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 7/19/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 7/19/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 7/26/2024 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 3/19/2025 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 3/24/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Final | 3/24/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/1/2025 | Corrections Issued | RAUL BARAJAS |
| Gas Test | 4/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 4/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 4/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Test | 4/11/2025 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 4/11/2025 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 4/11/2025 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 4/28/2025 | Approved | BRIAN SULLIVAN |
| Gas Test | 5/6/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Not Ready | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/25/2025 | Approved | ENRIQUE MIRELES |
| Final | 6/25/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/25/2025 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/25/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 6/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 6/25/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 6/30/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 6/30/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 7/7/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 7/7/2025 | Not Required | RAUL BARAJAS |
| Final | 7/10/2025 | No Access for Inspection | NICHOLAS LOPEZ |
| Final | 7/14/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/17/2025 | Approved | RAUL BARAJAS |
| Final | 7/17/2025 | OK to Issue CofO | RAUL BARAJAS |