6950 N TUJUNGA AVE 91605
Certificate Information: 6950 N TUJUNGA AVE 91605
- Application / Permit
- 22010-20000-06332
- Plan Check / Job No.
- B22VN18721
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- eplan: CONSTRUCT A NEW ONE STORY AND MEZZANINE CONCRETE TILT-UP WAREHOUSE BUILDING; EQUIPPED WITH NFPA 13R FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/26/2023 | SELLA BENYAMIN |
| Quality Review Completed | 1/31/2023 | STEVEN KIM |
| Applicant returned to address corrections | 3/23/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 4/18/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 5/18/2023 | SELLA BENYAMIN |
| Plan Check Approved | 1/25/2024 | SELLA BENYAMIN |
| Issued | 1/26/2024 | APPLICANT |
| CofO in Progress | 5/19/2025 | JOHN KITCKO |
| Permit Finaled | 5/29/2025 | JEFFREY DURAN |
| CofO Issued | 5/29/2025 | JEFFREY DURAN |
| Permit Finaled | 5/29/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/17/2023 | DAGOVERTO GUERRERO |
| Internal circulation | Cleared | 3/7/2023 | MIGUEL CRISOSTOMO |
| Trees in Parkway | Cleared | 3/22/2023 | ADALBERTO VERA |
| DAS Clearance | Cleared | 4/13/2023 | Shangqin Xie |
| Highway dedication | Cleared | 4/19/2023 | LEE GUILBEAUX |
| Permit | Cleared | 4/19/2023 | LEE GUILBEAUX |
| Metro Rail approval | Cleared | 7/17/2023 | JENNIFER SU |
| Hydrant and Access approval | Cleared | 7/24/2023 | KURT CORRAL |
| Green Code | Cleared | 9/15/2023 | MICHAEL AYERS |
| Low Impact Development | Cleared | 10/29/2023 | MARTIN FRAGOSO |
| Stormwater Pollution Mitigatn | Cleared | 10/29/2023 | MARTIN FRAGOSO |
| Miscellaneous | Cleared | 11/8/2023 | ANNA VIDAL |
| Prkng lot landscape/Water mgmt | Cleared | 11/8/2023 | ANNA VIDAL |
| Roof/Waste drainage to street | Cleared | 1/18/2024 | NIKKI ZULUETA |
Contact Information
| Contractor | Millie And Severson General Contractors; Lic. No.: 99031-B | 2459 LEE AVE SOUTH EL MONTE, CA 91733 |
| Contractor | Millie And Severson Incorporated; Lic. No.: 99031-B | 2459 LEE AVE SOUTH EL MONTE, CA 91733 |
| Engineer | Kramer,, David; Lic. No.: S2309 | 3002 DOW AVENUE SUITE 136 TUSTIN, CA 92680 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 4/1/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 4/2/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/3/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/8/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/9/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Corrections Issued | ROBERT DAVIS |
| Deputy Steel/Welding | 4/10/2024 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 4/12/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 4/18/2024 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 4/19/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/19/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/19/2024 | Corrections Issued | JOHN KITCKO |
| Green Building Rough | 4/20/2024 | Not Ready for Inspection | JOHN KITCKO |
| Reinforced Concrete Frame | 4/20/2024 | Partial Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 4/20/2024 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 4/23/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/24/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/26/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/26/2024 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 4/26/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/30/2024 | Partial Approval | JOHN KITCKO |
| Wood Frame | 5/7/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 5/10/2024 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 5/13/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 5/16/2024 | Conditional Approval | JOHN KITCKO |
| Wood Frame | 5/22/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 5/30/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 6/3/2024 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 6/4/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 6/6/2024 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 6/13/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 6/14/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 6/24/2024 | No Access for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 6/24/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 6/25/2024 | Partial Approval | JOHN KITCKO |
| Wood Frame | 7/1/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 7/2/2024 | Partial Approval | ROBERT DAVIS |
| Reinforced Concrete Frame | 7/2/2024 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 7/8/2024 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/12/2024 | Partial Approval | JOHN KITCKO |
| Wood Frame | 7/12/2024 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 7/15/2024 | Partial Approval | JOHN KITCKO |
| Wood Frame | 7/19/2024 | Not Ready for Inspection | JOHN KITCKO |
| T-Bar Ceiling | 7/29/2024 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 8/16/2024 | No Access for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 8/20/2024 | Partial Approval | JOHN KITCKO |
| Final | 4/8/2025 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 4/8/2025 | Approved | JOHN KITCKO |
| Green Building Final | 4/8/2025 | Approved | JOHN KITCKO |
| Green Building Rough | 4/8/2025 | Approved | JOHN KITCKO |
| Reinforced Concrete Frame | 4/8/2025 | Approved | JOHN KITCKO |
| Reinforced Masonry Frame | 4/8/2025 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV No Gas | JOHN KITCKO |
| Smoke Detectors | 4/8/2025 | Approved | JOHN KITCKO |
| Verify Sprinkler Sign Off | 4/8/2025 | Approved | JOHN KITCKO |
| Final | 5/9/2025 | Conditional Approval | JOHN KITCKO |
| Final | 5/19/2025 | OK to Issue CofO | JOHN KITCKO |