1701 N COLDWATER CANYON DR 90210
Certificate Information: 1701 N COLDWATER CANYON DR 90210
- Application / Permit
- 22010-20000-06316
- Plan Check / Job No.
- B22VN18674
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE & 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(e) PER ZA-2023-202-F-CU1-HCA [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- Current Status
- Issued on 8/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/16/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/23/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/24/2023 | APPLICANT |
| Applicant returned to address corrections | 6/30/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/7/2025 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/27/2025 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/18/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/26/2025 | NILOOFAR MEHRAIN |
| Issued | 8/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2023 | ANTHONY MAINEZ |
| Permit | Cleared | 3/1/2023 | ANTHONY MAINEZ |
| Street Frontage | Cleared | 3/1/2023 | ANTHONY MAINEZ |
| Disturb/Remove Protected Trees | Cleared | 4/3/2023 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/3/2023 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 4/4/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 4/13/2023 | KURT CORRAL |
| Haul Route | Cleared | 5/13/2024 | NILOOFAR MEHRAIN |
| Low Impact Development (LID) | Cleared | 7/1/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | BRENDEN HAWK |
| ZA Case | Cleared | 3/26/2025 | ROSALINDA MEZA |
| GPI Written Notices | Cleared | 5/13/2025 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 5/13/2025 | NILOOFAR MEHRAIN |
| Excavation more than 5-ft deep | Cleared | 5/27/2025 | CALOSHA APPROVED |
Contact Information
| Architect | Manion,, Richard M; Lic. No.: C26957 | 11400 WEST OLYMPIC BLVD SUITE 410 LOS ANGELES, CA 90025 |
| Contractor | Owner-Builder | , |
| Engineer | Guzman,, Martin; Lic. No.: C79193 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Other (see comments) | 2/9/2026 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 2/9/2026 | Partial Approval | CRAIG VAUGHAN |
| Deputy Steel/Welding | 2/13/2026 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 2/25/2026 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 2/25/2026 | Partial Approval | DAVID WILLIAMS |
| Sewer | 2/25/2026 | Partial Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 3/6/2026 | Partial Approval | DAVID WILLIAMS |
| Grading Pre-Inspection | 3/6/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Sewer | 3/6/2026 | Partial Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 3/23/2026 | Partial Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 4/1/2026 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 4/20/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 4/20/2026 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/21/2026 | Partial Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Insulation | 4/23/2026 | Partial Approval | DAVID WILLIAMS |
| Deputy Wood Construction | 4/24/2026 | Conditional Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2026 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Partial Approval | BRENDAN MORELLI |
| Wood Frame | 5/26/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Deputy Steel/Welding | 7/8/2026 | Conditional Approval | BRENDAN MORELLI |