16049 W BRYANT ST 91343

Certificate Information: 16049 W BRYANT ST 91343

Application / Permit
22010-20000-06297
Plan Check / Job No.
B22VN18643
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 40' X 44'-8" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED REC ROOM ALL WORK PER WFPP
Permit Issued
Issued on 6/22/2023
Issuing Office
Current Status
CofO Issued on 6/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 2/2/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 2/3/2023 OMID HEDAYAT
Building Plans Picked Up 2/7/2023 APPLICANT
Plan Check Approved 6/22/2023 SEWADA ZADOORAN MILAGARDI
Issued 6/22/2023 APPLICANT
CofO in Progress 5/5/2025 KEVIN BERBERYAN
CofO Issued 6/27/2025 RUBEN SALAS
Permit Finaled 6/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/8/2023 LEE GUILBEAUX
Address approval Cleared 3/8/2023 LEE GUILBEAUX
Miscellaneous Cleared 4/24/2023 ASHLEY RODARTE
ZI Cleared 4/24/2023 ASHLEY RODARTE
Miscellaneous Cleared 5/19/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/22/2023 LEE GUILBEAUX
Sewer availability Cleared 5/22/2023 LEE GUILBEAUX
Stormwater Pollution Mitigatn Cleared 6/2/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/20/2023 LEE GUILBEAUX
Construction near power lines Cleared 6/21/2023 WALTER RAMIREZ
Construction within easement Cleared 6/21/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/30/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 8/30/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 9/7/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/20/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 11/20/2023 Approved RAUL OLAGI
Green Building Rough 11/20/2023 Approved RAUL OLAGI
HVAC-Rough 11/20/2023 Approved RAUL OLAGI
PLUMBING-Rough 11/20/2023 Approved RAUL OLAGI
Sewer 11/20/2023 Approved RAUL OLAGI
Underground Mechanical 11/20/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 11/20/2023 Approved RAUL OLAGI
Insulation 1/10/2024 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 1/10/2024 Corrections Issued RAUL OLAGI
Insulation 3/8/2024 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 3/8/2024 Partial Approval RAUL OLAGI
Insulation 4/24/2024 Approved RAUL OLAGI
Drywall Nailing 5/13/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 5/13/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 5/22/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 5/22/2024 Approved RAUL OLAGI
Underground Mechanical 5/22/2024 Approved RAUL OLAGI
Service/Power Release 6/26/2024 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 6/26/2024 Approved RAUL OLAGI
Final 2/19/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/19/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 2/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 2/19/2025 Approved GAREN HAYRAPETYAN
Final 3/6/2025 Corrections Issued SALVADOR MARTINEZ
Service/Power Release 3/6/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 4/4/2025 Corrections Issued SALVADOR MARTINEZ
Service/Power Release 4/4/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 4/25/2025 Corrections Issued SALVADOR MARTINEZ
Service/Power Release 4/25/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 5/2/2025 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 5/2/2025 Not Required KEVIN BERBERYAN