9929 W ANTHONY PL 90210

Certificate Information: 9929 W ANTHONY PL 90210

Application / Permit
22010-20000-06289
Plan Check / Job No.
B22VN18620
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 71'10"X63'0" IRREGULAR SHAPED 2-STORY SFR W/ GARAGE. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 11/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 MARVEL DELACRUZ
Corrections Issued 1/25/2023 MARVEL DELACRUZ
Quality Review Completed 1/26/2023 OMID HEDAYAT
Building Plans Picked Up 1/30/2023 APPLICANT
Applicant returned to address corrections 7/19/2023 MARVEL DELACRUZ
Applicant returned to address corrections 11/2/2023 MARVEL DELACRUZ
Plan Check Approved 11/6/2023 MARVEL DELACRUZ
Issued 11/6/2023 APPLICANT
CofO in Progress 7/22/2025 SEAN HAUPT
Permit Finaled 7/29/2025 RICHARD STEINBACH
CofO Issued 7/29/2025 RICHARD STEINBACH
Permit Finaled 7/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/27/2023 DARIN LAM
BHO/Hillside ordinance Cleared 6/27/2023 DARIN LAM
BHO/Hillside ordinance Cleared 6/27/2023 DARIN LAM
BHO/Hillside ordinance Cleared 6/27/2023 DARIN LAM
BHO/Hillside ordinance Cleared 6/27/2023 DARIN LAM
Permit Cleared 6/27/2023 DARIN LAM
Trees in Parkway Cleared 7/3/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 8/21/2023 LAVEON RIDER
Low Impact Development Cleared 9/7/2023 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 9/20/2023 DARIN LAM
Sewer availability Cleared 9/20/2023 DARIN LAM
Roof/Waste drainage to street Cleared 9/27/2023 AHMED AMARRAGY
Distance to fire station Cleared 10/17/2023 LAVEON RIDER
BHO/Hillside ordinance Cleared 10/26/2023 DINAH GARIN

Contact Information

Contractor Brody Inc; Lic. No.: 409492-B 14140 MOORPARK ST #400      SHERMAN OAKS, CA 91423
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/20/2023 Conditional Approval BRENDAN LOONEY
Piling/Pier/Caisson 11/20/2023 Partial Approval BRENDAN LOONEY
Piling/Pier/Caisson 11/21/2023 Approved BRENDAN LOONEY
Deputy Other (see comments) 11/22/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 12/7/2023 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/7/2023 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 12/7/2023 Conditional Approval BRENDAN LOONEY
Deputy Reinf. Concrete 12/8/2023 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 12/14/2023 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 12/19/2023 Conditional Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 1/18/2024 Partial Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 1/19/2024 Corrections Issued BRENDAN LOONEY
Deputy Reinf. Concrete 1/24/2024 Conditional Approval MICHAEL PELHAM
Deputy Shotcrete 1/31/2024 Conditional Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 2/15/2024 Corrections Issued SEAN HAUPT
Excavation/Setback/Form/Re-Bar 2/16/2024 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 2/26/2024 Partial Approval SEAN HAUPT
Deputy Wood Construction 3/11/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Corrections Issued SEAN HAUPT
Wood Frame 6/21/2024 Approved SEAN HAUPT
PLUMBING-Rough 6/28/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 7/10/2024 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 7/10/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 7/25/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/31/2024 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 7/31/2024 Approved SEAN HAUPT
Green Building Rough 7/31/2024 Approved SEAN HAUPT
Verify Sprinkler Sign Off 7/31/2024 Approved SEAN HAUPT
Insulation 8/8/2024 Not Ready for Inspection SEAN HAUPT
Insulation 8/9/2024 Approved SEAN HAUPT
Drywall Nailing 8/20/2024 Approved SEAN HAUPT
Sewer 9/20/2024 Approved SEAN HAUPT
Underground Mechanical 9/25/2024 Not Ready for Inspection SEAN HAUPT
Shower Pan 9/26/2024 Approved SEAN HAUPT
Underground Mechanical 9/26/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 10/11/2024 Approved STEPHANIE SWANSON
Underground Mechanical 10/11/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/16/2025 Corrections Issued SEAN HAUPT
PLUMBING-Final 4/16/2025 Partial Approval SEAN HAUPT
ELECTRICAL-Final 4/24/2025 Approved SEAN HAUPT
Service/Power Release 4/24/2025 Approved SEAN HAUPT
Smoke Detectors 4/24/2025 Approved SEAN HAUPT
HVAC-Final 6/25/2025 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 7/9/2025 Approved SEAN HAUPT
Final 7/9/2025 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 7/9/2025 Approved SEAN HAUPT
Green Building Final 7/9/2025 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved SEAN HAUPT
Final 7/21/2025 OK to Issue CofO SEAN HAUPT