6571 N PONCE AVE 91307

Certificate Information: 6571 N PONCE AVE 91307

Application / Permit
22010-20000-06288
Plan Check / Job No.
B22VN18619
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY (41'-0"x32'-6"),1199 SQFT ADU PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 1/24/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 PETER MOSESIAN
Corrections Issued 1/7/2023 PETER MOSESIAN
Quality Review Completed 1/10/2023 OMID HEDAYAT
Building Plans Picked Up 1/10/2023 APPLICANT
Plan Check Approved 1/24/2023 PETER MOSESIAN
Issued 1/24/2023 APPLICANT
CofO in Progress 4/4/2024 TROY SANDERS
Permit Finaled 4/18/2024 JOHN JANSON
CofO Issued 4/18/2024 JOHN JANSON
Permit Finaled 4/18/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/9/2023 CARLOS AGUILERA
Construction near power lines Cleared 1/9/2023 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/9/2023 CARLOS AGUILERA
Sewer availability Cleared 1/9/2023 CARLOS AGUILERA
Low Impact Development Cleared 1/18/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/18/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khansa,, Eyass Wafik; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/10/2023 Partial Approval TROY SANDERS
Sewer 4/19/2023 Approved TROY SANDERS
Special/Order Compliance 4/19/2023 Partial Inspection MORRIS JACKSON
Footing/Foundation/Slab 4/21/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 5/25/2023 Partial Approval TROY SANDERS
ELECTRICAL-Rough 5/25/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Approved TROY SANDERS
PLUMBING-Rough 5/25/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 7/14/2023 Approved TROY SANDERS
Green Building Rough 7/14/2023 Approved TROY SANDERS
Insulation 7/14/2023 Approved TROY SANDERS
Interior/Exterior Lathing 7/14/2023 Partial Approval TROY SANDERS
Verify Sprinkler Sign Off 7/14/2023 Approved TROY SANDERS
Drywall Nailing 7/28/2023 Approved TROY SANDERS
Shower Pan 7/28/2023 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 8/10/2023 Partial Approval TROY SANDERS
Shower Pan 8/10/2023 Approved TROY SANDERS
Final 11/6/2023 Not Ready for Inspection HORACE FULTZ
Green Building Final 11/6/2023 Not Ready for Inspection HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 11/6/2023 SGSOV Approved HORACE FULTZ
Service/Power Release 11/6/2023 Approved HORACE FULTZ
Smoke Detectors 11/6/2023 Approved HORACE FULTZ
Final 2/15/2024 Not Ready for Inspection TROY SANDERS
Green Building Final 2/15/2024 Not Ready for Inspection TROY SANDERS
Final 3/12/2024 Corrections Issued TROY SANDERS
Green Building Final 3/12/2024 Approved TROY SANDERS
Final 3/29/2024 Not Ready for Inspection GEVORK IPCHYAN
Final 4/4/2024 OK to Issue CofO TROY SANDERS