14834 W CALAHAN ST 91402
Certificate Information: 14834 W CALAHAN ST 91402
- Application / Permit
- 22010-20000-06280
- Plan Check / Job No.
- B22VN18594
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 18'-8"x31'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2023 | SERGIO MUNIZ |
| Corrections Issued | 1/26/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 2/2/2023 | APPLICANT |
| Applicant returned to address corrections | 10/2/2023 | MOHAMMAD ESMAILI |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 4/29/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 5/14/2025 | RUBEN SALAS |
| CofO Issued | 5/14/2025 | RUBEN SALAS |
| Permit Finaled | 5/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/15/2023 | NIKKI ZULUETA |
| Address approval | Cleared | 6/16/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 6/20/2023 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 9/28/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/29/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | E N B Construction Inc; Lic. No.: 990795-B | 15115 PARTHENIA ST APT #232 NORTH HILLS, CA 91343 |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/29/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 12/11/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 12/11/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 12/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 12/14/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Deck | 12/20/2023 | No Access for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | No Access for Inspection | KEVIN BERBERYAN |
| Deck | 12/26/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Deck | 12/28/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/12/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/12/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/12/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Wood Construction | 1/16/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/19/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 1/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 1/24/2024 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/24/2024 | Partial Approval | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 1/24/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/30/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/7/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/7/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/23/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 5/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/23/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/23/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 5/23/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/30/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/30/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 8/29/2024 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 8/29/2024 | Not Required | JACK KARGODORIAN |
| Final | 10/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/18/2025 | Approved | JENNIFER RABUCHIN |
| Final | 4/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 4/18/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/18/2025 | Approved | JENNIFER RABUCHIN |
| Final | 4/30/2025 | OK to Issue CofO | JENNIFER RABUCHIN |