4438 N CANOGA DR 91364

Certificate Information: 4438 N CANOGA DR 91364

Application / Permit
22010-20000-06277
Plan Check / Job No.
B22VN18589
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 15'3" X 14'1" DETACHED RECREATION ROOM WITH ATTACHED 12'8" X 4'11" BATHROOM AND OUTDOOR SHOWER. WORK DONE PER ENGINEERING. **NFPA-13D FIRE SPRINKLERS TO BE INSTALLED THROUGHOUT**
Permit Issued
Issued on 8/9/2023
Issuing Office
Current Status
CofO Corrected on 5/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/27/2022 DANIEL YIP
Corrections Issued 12/27/2022 DANIEL YIP
Applicant returned to address corrections 1/24/2023 MADISON ODELL
Applicant returned to address corrections 5/13/2023 MADISON ODELL
Applicant returned to address corrections 7/11/2023 MADISON ODELL
Plan Check Approved 8/4/2023 MADISON ODELL
Issued 8/9/2023 APPLICANT
CofO in Progress 4/23/2024 MORRIS JACKSON
CofO Issued-Status Void 5/8/2024 JOHN JANSON
Permit Finaled-Status Void 5/8/2024 JOHN JANSON
Re-Activate Permit 5/9/2024 JOHN JANSON
Permit Finaled 5/9/2024 JOHN JANSON
CofO Corrected 5/9/2024 JOHN JANSON
Permit Finaled 5/9/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/3/2023 MEGAN GODINEZ
Sewer availability Cleared 1/3/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 1/5/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 1/5/2023 MEGAN GODINEZ
Specific Plan Cleared 4/20/2023 OLGA AYALA
Specific Plan Cleared 4/20/2023 OLGA AYALA
Eng Process Fee Ord 176,300 Cleared 7/3/2023 MEGAN GODINEZ
Grading Pre-Inspection Cleared 8/4/2023 MADISON ODELL

Contact Information

Contractor M D R N Remodeling Company; Lic. No.: 1065843-B       ,
Contractor Mdrn Construction; Lic. No.: 1065843-B       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/14/2023 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 8/14/2023 Corrections Issued PETER FOLLING
PLUMBING-Rough 8/14/2023 Corrections Issued PETER FOLLING
PLUMBING-Rough 8/15/2023 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 8/16/2023 Partial Approval PETER FOLLING
Sewer 8/16/2023 Approved PETER FOLLING
Excavation/Setback/Form/Re-Bar 9/7/2023 Corrections Issued PETER FOLLING
Deputy Reinf. Concrete 9/21/2023 No Access for Inspection PETER FOLLING
Excavation/Setback/Form/Re-Bar 9/22/2023 Approved PETER FOLLING
ELECTRICAL-Rough 10/27/2023 Approved PETER FOLLING
PLUMBING-Rough 10/27/2023 Corrections Issued PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Approved PETER FOLLING
PLUMBING-Rough 11/1/2023 Approved PETER FOLLING
Interior/Exterior Lathing 12/18/2023 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 1/12/2024 Approved JOHN KIDWELL
Green Building Rough 1/12/2024 Approved JOHN KIDWELL
Insulation 1/12/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 1/12/2024 Approved JOHN KIDWELL
Drywall Nailing 1/23/2024 Approved JOHN KIDWELL
Shower Pan 1/23/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/2/2024 Partial Approval JOHN KIDWELL
Final 4/8/2024 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 4/8/2024 Approved MORRIS JACKSON
Green Building Final 4/8/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 4/8/2024 Partial Inspection MORRIS JACKSON
Smoke Detectors 4/8/2024 Approved MORRIS JACKSON
Final 4/22/2024 OK to Issue CofO MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Approved MORRIS JACKSON
Service/Power Release 4/22/2024 Approved MORRIS JACKSON