14822-14824 W VANOWEN ST 91405

Certificate Information: 14822-14824 W VANOWEN ST 91405

Application / Permit
22010-20000-06212
Plan Check / Job No.
B22VN18451
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: PROPOSED 2-STORY DUPLEX (TWO ACCESSORY DWELLING UNITS) PER STATE LAW GCS 65852.2(e)(1)(D).
Permit Issued
Issued on 8/8/2023
Issuing Office
Current Status
CofO Issued on 5/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 MICHAEL LOPEZ
Corrections Issued 1/27/2023 MICHAEL LOPEZ
Quality Review Completed 1/27/2023 GARO TELMI
Applicant returned to address corrections 6/8/2023 MICHAEL LOPEZ
Applicant returned to address corrections 7/10/2023 MICHAEL LOPEZ
Plan Check Approved 8/3/2023 MICHAEL LOPEZ
No Progress 8/8/2023 MICHAEL LOPEZ
Plan Check Approved 8/8/2023 MICHAEL LOPEZ
Issued 8/8/2023 APPLICANT
CofO in Progress 5/13/2024 RYAN SALAZAR
Permit Finaled 5/18/2024 RUBEN SALAS
CofO Issued 5/18/2024 RUBEN SALAS
Permit Finaled 5/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/9/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/9/2023 CARLOS AGUILERA
Highway dedication Cleared 2/9/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/9/2023 CARLOS AGUILERA
Sewer availability Cleared 2/9/2023 CARLOS AGUILERA
"Q" conditions Cleared 3/6/2023 BRENNEN OBETO
Frnt yard landscape/Water mgmt Cleared 3/6/2023 BRENNEN OBETO
Miscellaneous Cleared 3/6/2023 BRENNEN OBETO
SB8 RUD Cleared 3/16/2023 JESSICA WANG
Hydrant and Access approval Cleared 5/15/2023 KURT CORRAL

Contact Information

Architect Hanna,, Remon; Lic. No.: NA36271       ,
Contractor Owner-Builder       ,
Engineer Hanna,, Emil Ramzy; Lic. No.: NA63602       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/12/2023 Partial Inspection RYAN SALAZAR
Sewer 10/19/2023 Approved RYAN SALAZAR
Underground Mechanical 10/19/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/31/2023 Approved RYAN SALAZAR
Special/Order Compliance 10/31/2023 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 11/20/2023 Corrections Issued RYAN SALAZAR
Green Building Rough 11/20/2023 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 11/20/2023 Not Ready for Inspection RYAN SALAZAR
Wood Frame 11/20/2023 Not Ready for Inspection RYAN SALAZAR
Rough-Elec/Plmb/HVAC 12/8/2023 Partial Approval RYAN SALAZAR
Shower Pan 12/8/2023 Approved RYAN SALAZAR
Wood Frame 12/8/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 12/19/2023 Corrections Issued RYAN SALAZAR
Green Building Rough 12/19/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/19/2023 Conditional Approval RYAN SALAZAR
Verify Sprinkler Sign Off 12/19/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 1/11/2024 Approved RYAN SALAZAR
PLUMBING-Rough 1/11/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 1/11/2024 Approved RYAN SALAZAR
Insulation 1/12/2024 Approved RYAN SALAZAR
Drywall Nailing 1/17/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 3/29/2024 Corrections Issued RYAN SALAZAR
Final 3/29/2024 Corrections Issued RYAN SALAZAR
Green Building Final 3/29/2024 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 3/29/2024 Approved RYAN SALAZAR
PLUMBING-Final 3/29/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 3/29/2024 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 3/29/2024 Approved RYAN SALAZAR
Final 5/6/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/6/2024 Approved RYAN SALAZAR
Service/Power Release 5/6/2024 Approved RYAN SALAZAR