964 N STONE CANYON ROAD 90077
Certificate Information: 964 N STONE CANYON ROAD 90077
- Application / Permit
- 22010-20000-06210
- Plan Check / Job No.
- B22VN18435
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY (19'-0"x40'-0"), 731 SQFT ACCESSORY DWELLING UNIT W/DECK ABOVE, ALL ON PILES AND GRADE BEAMS W/NPFA 13R SPRINKLERS THROUGHOUT PER 65852.2(e)(D) & LAMC 12.22 A.33(c)(d)(g)
- Permit Issued
- Issued on 1/3/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | PETER MOSESIAN |
| Corrections Issued | 1/26/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 2/2/2023 | APPLICANT |
| Plan Check Approved | 1/3/2024 | PETER MOSESIAN |
| Issued | 1/3/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | CHRISTOPHER WILSON |
| Permit Finaled | 5/27/2025 | RICHARD STEINBACH |
| CofO Issued | 5/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2023 | JENSON LEE |
| ZA Case | Cleared | 2/21/2023 | BRENNEN OBETO |
| BHO/Hillside ordinance | Cleared | 2/27/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 2/27/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 2/27/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 2/27/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 2/27/2023 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/27/2023 | JENSON LEE |
| Street Frontage | Cleared | 2/27/2023 | JENSON LEE |
| Watercourse | Cleared | 2/28/2023 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 4/6/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 6/1/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/7/2023 | DINAH GARIN |
| Flood clearance | Cleared | 12/21/2023 | ABDULRAHMAN ALABTAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/18/2024 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 1/18/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/19/2024 | Conditional Approval | MICHAEL PELHAM |
| Underground Mechanical | 3/6/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Underground Mechanical | 3/7/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Underground Mechanical | 3/14/2024 | Partial Approval | CHRISTOPHER WILSON |
| FLOOD-Elevation Certificate | 3/20/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/20/2024 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/27/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 3/28/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/7/2024 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 5/8/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/18/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/26/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 6/26/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/26/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Wood Frame | 6/26/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Underground Mechanical | 6/29/2024 | Off-Hour Fees Due | |
| Underground Mechanical | 6/29/2024 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 7/1/2024 | Partial Approval | MICHAEL PELHAM |
| FLOOD-Proofing Certificate | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 7/2/2024 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 7/2/2024 | Partial Approval | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 7/2/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/17/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/23/2024 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/23/2024 | Approved | CHRISTOPHER WILSON |
| Final | 7/23/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/23/2024 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/23/2024 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 7/23/2024 | Approved | CHRISTOPHER WILSON |
| Insulation | 8/6/2024 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 8/8/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 8/8/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/15/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 8/26/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 11/22/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/25/2024 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/10/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 1/28/2025 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 2/10/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Pre-Inspection | 5/16/2025 | Conditional Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| FLOOD-Elevation Certificate | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| FLOOD-Proofing Certificate | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| Final | 5/19/2025 | OK to Issue CofO | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | CHRISTOPHER WILSON |
| Service/Power Release | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 5/19/2025 | Approved | CHRISTOPHER WILSON |