5799 N RANCHITO AVE 91401

Certificate Information: 5799 N RANCHITO AVE 91401

Application / Permit
22010-20000-06205
Plan Check / Job No.
B22VN18405
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW 37'9"X70'4" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e) W/ ATTACHED GARAGE, PORCH & PATIO COVER.
Permit Issued
Issued on 6/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 HAYATO TSUCHIYA
Corrections Issued 12/17/2022 HAYATO TSUCHIYA
Building Plans Picked Up 12/23/2022 APPLICANT
Applicant returned to address corrections 5/17/2023 JESSE ARELLANO
Plan Check Approved 6/7/2023 MOHAMMAD ESMAILI
Issued 6/13/2023 APPLICANT
CofO in Progress 5/12/2025 RYAN SALAZAR
Permit Finaled 6/13/2025 RUBEN SALAS
CofO Issued 6/13/2025 RUBEN SALAS
Permit Finaled 6/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/27/2022 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 12/28/2022 RYAN KIM
Sewer availability Cleared 12/28/2022 RYAN KIM
Construction near power lines Cleared 1/10/2023 RIDWAN HARDY
Low Impact Development Cleared 4/24/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/25/2023 RYAN KIM

Contact Information

Contractor Gabe Kaprelian Electrical Contractor; Lic. No.: 321040-B 5801 RANCHITO AVE      VAN NUYS, CA 91401
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

RYAN SALAZAR, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/13/2024 Partial Inspection RYAN SALAZAR
ELECTRICAL-Rough 3/19/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 3/19/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 4/4/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 4/11/2024 Approved RYAN SALAZAR
Deputy Wood Construction 6/7/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/22/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 7/22/2024 Approved RYAN SALAZAR
Green Building Rough 7/22/2024 Approved RYAN SALAZAR
HVAC-Rough 7/22/2024 Approved RYAN SALAZAR
PLUMBING-Rough 7/22/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 7/22/2024 Approved RYAN SALAZAR
Insulation 8/9/2024 Approved RYAN SALAZAR
Shower Pan 8/9/2024 Approved RYAN SALAZAR
Underground Mechanical 8/9/2024 Approved RYAN SALAZAR
Sewer 8/14/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/26/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 8/29/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/6/2024 Approved RYAN SALAZAR
Shower Pan 9/6/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 12/5/2024 Partial Approval RYAN SALAZAR
PLUMBING-Final 12/5/2024 Approved RYAN SALAZAR
Green Building Final 1/7/2025 Approved RYAN SALAZAR
Final 5/8/2025 OK to Issue CofO RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved RYAN SALAZAR
Service/Power Release 5/8/2025 Approved RYAN SALAZAR
Smoke Detectors 5/8/2025 Approved RYAN SALAZAR