5799 N RANCHITO AVE 91401
Certificate Information: 5799 N RANCHITO AVE 91401
- Application / Permit
- 22010-20000-06205
- Plan Check / Job No.
- B22VN18405
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW 37'9"X70'4" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e) W/ ATTACHED GARAGE, PORCH & PATIO COVER.
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 12/15/2022 | APPLICANT |
Assigned to Plan Check Engineer | 12/16/2022 | HAYATO TSUCHIYA |
Corrections Issued | 12/17/2022 | HAYATO TSUCHIYA |
Building Plans Picked Up | 12/23/2022 | APPLICANT |
Applicant returned to address corrections | 5/17/2023 | JESSE ARELLANO |
Plan Check Approved | 6/7/2023 | MOHAMMAD ESMAILI |
Issued | 6/13/2023 | APPLICANT |
CofO in Progress | 5/12/2025 | RYAN SALAZAR |
Permit Finaled | 6/13/2025 | RUBEN SALAS |
CofO Issued | 6/13/2025 | RUBEN SALAS |
Permit Finaled | 6/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
Address approval | Cleared | 12/27/2022 | RYAN KIM |
Eng Process Fee Ord 176,300 | Cleared | 12/28/2022 | RYAN KIM |
Sewer availability | Cleared | 12/28/2022 | RYAN KIM |
Construction near power lines | Cleared | 1/10/2023 | RIDWAN HARDY |
Low Impact Development | Cleared | 4/24/2023 | MELINEH AGHAKHABIAN |
Roof/Waste drainage to street | Cleared | 4/25/2023 | RYAN KIM |
Contact Information
Contractor | Gabe Kaprelian Electrical Contractor; Lic. No.: 321040-B | 5801 RANCHITO AVE VAN NUYS, CA 91401 |
Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
RYAN SALAZAR, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 3/13/2024 | Partial Inspection | RYAN SALAZAR |
ELECTRICAL-Rough | 3/19/2024 | Partial Approval | RYAN SALAZAR |
PLUMBING-Rough | 3/19/2024 | Partial Approval | RYAN SALAZAR |
Footing/Foundation/Slab | 4/4/2024 | Partial Approval | RYAN SALAZAR |
Footing/Foundation/Slab | 4/11/2024 | Approved | RYAN SALAZAR |
Deputy Wood Construction | 6/7/2024 | Conditional Approval | DAVID MATSON |
Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Approved | RYAN SALAZAR |
BUILDING-Rough-Frame | 7/22/2024 | Approved | RYAN SALAZAR |
ELECTRICAL-Rough | 7/22/2024 | Approved | RYAN SALAZAR |
Green Building Rough | 7/22/2024 | Approved | RYAN SALAZAR |
HVAC-Rough | 7/22/2024 | Approved | RYAN SALAZAR |
PLUMBING-Rough | 7/22/2024 | Approved | RYAN SALAZAR |
Verify Sprinkler Sign Off | 7/22/2024 | Approved | RYAN SALAZAR |
Insulation | 8/9/2024 | Approved | RYAN SALAZAR |
Shower Pan | 8/9/2024 | Approved | RYAN SALAZAR |
Underground Mechanical | 8/9/2024 | Approved | RYAN SALAZAR |
Sewer | 8/14/2024 | Approved | RYAN SALAZAR |
Interior/Exterior Lathing | 8/26/2024 | Partial Approval | RYAN SALAZAR |
Drywall Nailing | 8/29/2024 | Approved | RYAN SALAZAR |
Interior/Exterior Lathing | 9/6/2024 | Approved | RYAN SALAZAR |
Shower Pan | 9/6/2024 | Approved | RYAN SALAZAR |
ELECTRICAL-Final | 12/5/2024 | Partial Approval | RYAN SALAZAR |
PLUMBING-Final | 12/5/2024 | Approved | RYAN SALAZAR |
Green Building Final | 1/7/2025 | Approved | RYAN SALAZAR |
Final | 5/8/2025 | OK to Issue CofO | RYAN SALAZAR |
SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | RYAN SALAZAR |
Service/Power Release | 5/8/2025 | Approved | RYAN SALAZAR |
Smoke Detectors | 5/8/2025 | Approved | RYAN SALAZAR |