7661-7663 N MAESTRO AVE 91304
Certificate Information: 7661-7663 N MAESTRO AVE 91304
- Application / Permit
- 22010-20000-06186
- Plan Check / Job No.
- B22VN18334
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: 1060 ft new detached 1-story 2nd unit per SB9 Two-Unit Development Ca Govt Code 65852.21, with 23.5 ft Porch and 600 ft ADU with 144 ft porch
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2022 | RAHEL BEYENE |
| Corrections Issued | 12/22/2022 | RAHEL BEYENE |
| Applicant returned to address corrections | 3/7/2023 | KHUONG TRUONG |
| Plan Check Approved | 3/22/2023 | RAHEL BEYENE |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 12/4/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 1/10/2024 | JOHN JANSON |
| CofO Issued | 1/10/2024 | JOHN JANSON |
| Permit Finaled | 1/10/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/22/2022 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 1/17/2023 | ASHLEY RODARTE |
| Low Impact Development | Cleared | 1/31/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 3/7/2023 | RAHEL BEYENE |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/16/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/26/2023 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/4/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 8/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 8/4/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 8/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/8/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 8/8/2023 | Approved | MORRIS JACKSON |
| Shower Pan | 8/8/2023 | Approved | MORRIS JACKSON |
| Underground Mechanical | 8/8/2023 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 8/14/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/14/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/14/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 8/21/2023 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 8/29/2023 | Approved | CHRIS CHRISTENSEN |
| Sewer | 10/6/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 10/30/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 10/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/30/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 11/15/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/15/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Service/Power Release | 11/15/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Inspection | 11/17/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 11/29/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/29/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Service/Power Release | 11/29/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/1/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 12/1/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 12/1/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 12/1/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/1/2023 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 12/1/2023 | Approved | CHRIS CHRISTENSEN |