10742 W AQUA VISTA ST 91602
Certificate Information: 10742 W AQUA VISTA ST 91602
- Application / Permit
- 22010-20000-06165
- Plan Check / Job No.
- B22VN18289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) Detached 2-story ADU
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Current Status
- CofO Issued on 6/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | HERNAN ARREOLA |
| Corrections Issued | 1/28/2023 | HERNAN ARREOLA |
| Quality Review Completed | 1/31/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/24/2023 | HERNAN ARREOLA |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 6/14/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 6/29/2024 | RUBEN SALAS |
| CofO Issued | 6/29/2024 | RUBEN SALAS |
| Permit Finaled | 6/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/18/2023 | CARLOS AGUILERA |
| Stormwater Pollution Mitigatn | Cleared | 4/7/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/1/2023 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 8/2/2023 | Partial Approval | JACK KARGODORIAN |
| Sewer | 8/2/2023 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/5/2023 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/17/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 11/9/2023 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Corrections Issued | JOHN COLEMAN |
| Insulation | 11/14/2023 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | KIRK SANDERS |
| Pre-Inspection | 1/11/2024 | Partial Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/19/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/12/2024 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 2/12/2024 | Corrections Issued | KIRK SANDERS |
| Verify Sprinkler Sign Off | 2/12/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/27/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/27/2024 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 2/27/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/18/2024 | Conditional Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 3/18/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 3/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 3/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/1/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/8/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/10/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 5/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 5/10/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Final | 5/10/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Final | 5/10/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 5/10/2024 | Partial Approval | KEVIN BERBERYAN |
| Smoke Detectors | 5/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 5/17/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/17/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 5/17/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 5/17/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/17/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/22/2024 | Approved | KEVIN BERBERYAN |
| Final | 5/22/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| HVAC-Final | 5/22/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 5/22/2024 | Approved | KEVIN BERBERYAN |