12050 N RED HAWK LANE 91326

Certificate Information: 12050 N RED HAWK LANE 91326

Application / Permit
22010-20000-06109
Plan Check / Job No.
B22VN18192
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE ONE STORY SFD WITH ATTACHED GARAGE (STANDARD PLAN 654 _ PLAN 6B) _ BUILDING SHALL BE FULLY SPRINKLER WITH NFPA 13D.
Permit Issued
Issued on 8/29/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 DAWN MC NULTY
Corrections Issued 2/13/2023 DAWN MC NULTY
Quality Review Completed 3/8/2023 STEVEN KIM
Building Plans Picked Up 3/13/2023 APPLICANT
Applicant returned to address corrections 9/19/2023 DAWN MC NULTY
Applicant returned to address corrections 8/9/2024 DAWN MC NULTY
Applicant returned to address corrections 8/12/2024 DAWN MC NULTY
Plan Check Approved 8/26/2024 DAWN MC NULTY
Issued 8/29/2024 APPLICANT
CofO in Progress 3/20/2025 JEFFREY PARD
Permit Finaled 3/20/2025 JOHN JANSON
CofO Issued 3/20/2025 JOHN JANSON
Permit Finaled 3/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/22/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/22/2023 LEE GUILBEAUX
Permit Cleared 8/22/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/22/2023 DAWN MC NULTY
Roof/Waste drainage to street Cleared 8/22/2023 LEE GUILBEAUX
Sewer availability Cleared 8/22/2023 LEE GUILBEAUX
Low Impact Development Cleared 8/23/2023 AMMAR ELTAWIL
Hydrant and Access approval Cleared 12/23/2023 JOHN CONNEALLY
"T" removal Cleared 8/12/2024 ASHLEY RODARTE
CPC Cleared 8/12/2024 ASHLEY RODARTE
CPC Cleared 8/12/2024 ASHLEY RODARTE
CPC Cleared 8/12/2024 ASHLEY RODARTE
Miscellaneous Cleared 8/12/2024 ASHLEY RODARTE
Miscellaneous Cleared 8/12/2024 ASHLEY RODARTE
Tract Map conditions Cleared 8/12/2024 ASHLEY RODARTE
ZA Case Cleared 8/12/2024 ASHLEY RODARTE
CPC Cleared 8/22/2024 ASHLEY RODARTE
Specific Plan Cleared 8/22/2024 ASHLEY RODARTE
Tract Map conditions Cleared 8/22/2024 ASHLEY RODARTE
GPI Written Notices Cleared 8/26/2024 DAWN MC NULTY
Grading Pre-Inspection Cleared 8/26/2024 DAWN MC NULTY
Miscellaneous Cleared 8/26/2024 DAWN MC NULTY

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Braatz,, Tara Elizabeth; Lic. No.: C79028 24855 CALLE CARMEL      LAGUNA HILLS, CA 92653
Engineer Hattar,, Basil; Lic. No.: GE2734 41837 SONOMA ROAD      PALMDALE, CA 93551
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/6/2024 Partial Approval JEFFREY PARD
Deputy Pre-Stress Concrete 9/27/2024 Approved JEFFREY PARD
Footing/Foundation/Slab 9/30/2024 Approved JEFFREY PARD
Deputy Reinf. Concrete 10/1/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Approved JEFFREY PARD
Special/Order Compliance 10/25/2024 Corrections Issued HENRY KIM
Underground Mechanical 10/25/2024 Approved HENRY KIM
Interior/Exterior Lathing 11/6/2024 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 11/13/2024 Approved JEFFREY PARD
HVAC-Rough 11/13/2024 Approved JEFFREY PARD
PLUMBING-Rough 11/13/2024 Approved JEFFREY PARD
Shower Pan 11/13/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 11/14/2024 Approved JEFFREY PARD
Green Building Rough 11/14/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 11/14/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 11/14/2024 Approved JEFFREY PARD
Insulation 11/19/2024 Approved JEFFREY PARD
Drywall Nailing 11/25/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 12/9/2024 Approved JEFFREY PARD
Sewer 12/18/2024 Partial Approval JEFFREY PARD
Gas Test 12/30/2024 Approved JEFFREY PARD
ELECTRICAL-Final 1/21/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved JEFFREY PARD
Service/Power Release 1/21/2025 Not Ready for Inspection JEFFREY PARD
Service/Power Release 1/29/2025 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved JEFFREY PARD
ELECTRICAL-Final 2/5/2025 Approved JEFFREY PARD
Service/Power Release 2/5/2025 Approved JEFFREY PARD
HVAC-Final 2/26/2025 Approved JEFFREY PARD
PLUMBING-Final 2/26/2025 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 3/3/2025 Approved JEFFREY PARD
Sewer 3/3/2025 Approved JEFFREY PARD
Final 3/14/2025 OK to Issue CofO JEFFREY PARD
Green Building Final 3/14/2025 Approved JEFFREY PARD
Smoke Detectors 3/14/2025 Approved JEFFREY PARD