8150 N TYRONE AVE 91402

Certificate Information: 8150 N TYRONE AVE 91402

Application / Permit
22010-20000-06011
Plan Check / Job No.
B22VN18052
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan NEW DETACHED ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/6/2023
Issuing Office
Current Status
CofO Issued on 3/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2022 APPLICANT
Assigned to Plan Check Engineer 12/23/2022 HANS SANTIAGO
Corrections Issued 12/23/2022 HANS SANTIAGO
Applicant returned to address corrections 7/17/2023 ALFREDO JARA
Applicant returned to address corrections 8/18/2023 ALFREDO JARA
Plan Check Approved 8/25/2023 ALFREDO JARA
Issued 9/6/2023 APPLICANT
CofO in Progress 3/1/2025 VINCENT HANLEY
Permit Finaled 3/11/2025 RUBEN SALAS
CofO Issued 3/11/2025 RUBEN SALAS
Permit Finaled 3/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/30/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/31/2023 LEE GUILBEAUX
Sewer availability Cleared 1/31/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 5/5/2023 KURT CORRAL
Construction near power lines Cleared 6/6/2023 RIDWAN HARDY
Construction within easement Cleared 6/6/2023 RIDWAN HARDY
Low Impact Development Cleared 8/16/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/17/2023 JOHN LIN

Contact Information

Architect Santillan,, Michael; Lic. No.: NA23337       ,
Contractor J & L Construction Services; Lic. No.: 948695-B       ,
Engineer Phan,, Ben; Lic. No.: NA57550       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/19/2023 No Access for Inspection GREGG CUMMINGS
Pre-Inspection 9/19/2023 No Access for Inspection GREGG CUMMINGS
PLUMBING-Rough 9/28/2023 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/3/2023 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/16/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/16/2023 Approved GREGG CUMMINGS
Wood Frame 11/29/2023 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 12/5/2023 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/12/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 12/12/2023 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/9/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/9/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 1/11/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 1/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/24/2024 Approved CHRISTOPHER ROJAS
Gas Test 1/24/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/24/2024 Approved CHRISTOPHER ROJAS
Insulation 1/30/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 2/1/2024 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 2/6/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 2/6/2024 Approved GREGG CUMMINGS
Insulation 2/6/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 2/12/2024 Approved WILLIAM WREN
Drywall Nailing 2/12/2024 Approved WILLIAM WREN
Green Building Rough 2/12/2024 Approved WILLIAM WREN
Verify Sprinkler Sign Off 2/12/2024 Approved WILLIAM WREN
Shower Pan 3/6/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 3/22/2024 Partial Approval GREGG CUMMINGS
Sewer 5/1/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/7/2024 Approved KIRK SANDERS
ELECTRICAL-Final 5/9/2024 Corrections Issued GREGG CUMMINGS
Underground Mechanical 5/9/2024 Partial Approval GREGG CUMMINGS
PLUMBING-Final 5/24/2024 Not Ready for Inspection JOHN COLEMAN
Service/Power Release 5/31/2024 Not Ready for Inspection GREGG CUMMINGS
Final 6/7/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 6/7/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 6/7/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 6/7/2024 Not Ready for Inspection GREGG CUMMINGS
Final 10/3/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 10/3/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Approved GREGG CUMMINGS
Service/Power Release 10/3/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 10/3/2024 Approved GREGG CUMMINGS
Final 10/23/2024 Not Ready for Inspection GREGG CUMMINGS
Service/Power Release 10/23/2024 Not Ready for Inspection GREGG CUMMINGS
Final 11/5/2024 Not Ready for Inspection VINCENT HANLEY
Service/Power Release 11/5/2024 Corrections Issued VINCENT HANLEY
Final 2/7/2025 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 2/7/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 2/28/2025 Approved VINCENT HANLEY
Final 2/28/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/28/2025 Approved VINCENT HANLEY
PLUMBING-Final 2/28/2025 Approved VINCENT HANLEY
Service/Power Release 2/28/2025 Approved VINCENT HANLEY