8150 N TYRONE AVE 91402
Certificate Information: 8150 N TYRONE AVE 91402
- Application / Permit
- 22010-20000-06011
- Plan Check / Job No.
- B22VN18052
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan NEW DETACHED ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | HANS SANTIAGO |
| Corrections Issued | 12/23/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/17/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 8/18/2023 | ALFREDO JARA |
| Plan Check Approved | 8/25/2023 | ALFREDO JARA |
| Issued | 9/6/2023 | APPLICANT |
| CofO in Progress | 3/1/2025 | VINCENT HANLEY |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
| CofO Issued | 3/11/2025 | RUBEN SALAS |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/31/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/5/2023 | KURT CORRAL |
| Construction near power lines | Cleared | 6/6/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/6/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/16/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | JOHN LIN |
Contact Information
| Architect | Santillan,, Michael; Lic. No.: NA23337 | , |
| Contractor | J & L Construction Services; Lic. No.: 948695-B | , |
| Engineer | Phan,, Ben; Lic. No.: NA57550 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/19/2023 | No Access for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 9/19/2023 | No Access for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 9/28/2023 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/16/2023 | Approved | GREGG CUMMINGS |
| Wood Frame | 11/29/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 12/5/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/12/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 12/12/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/9/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 1/11/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 1/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/24/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 1/24/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/24/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 1/30/2024 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/1/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/6/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 2/6/2024 | Approved | GREGG CUMMINGS |
| Insulation | 2/6/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/12/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 2/12/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 2/12/2024 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 2/12/2024 | Approved | WILLIAM WREN |
| Shower Pan | 3/6/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/22/2024 | Partial Approval | GREGG CUMMINGS |
| Sewer | 5/1/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/7/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 5/9/2024 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 5/9/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Final | 5/24/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 5/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 6/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 6/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 6/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/3/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/3/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 10/3/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/3/2024 | Approved | GREGG CUMMINGS |
| Final | 10/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 10/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 11/5/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Service/Power Release | 11/5/2024 | Corrections Issued | VINCENT HANLEY |
| Final | 2/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 2/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/28/2025 | Approved | VINCENT HANLEY |
| Final | 2/28/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 2/28/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/28/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 2/28/2025 | Approved | VINCENT HANLEY |