9414 N RUFFNER AVE 91343
Certificate Information: 9414 N RUFFNER AVE 91343
- Application / Permit
- 22010-20000-05977
- Plan Check / Job No.
- B22VN17986
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY (30'-7"x22'-10"), 1200 SQFT ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)(e)
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Current Status
- CofO Issued on 3/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | PETER MOSESIAN |
| Corrections Issued | 1/18/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/19/2023 | OMID HEDAYAT |
| Plan Check Approved | 5/23/2023 | PETER MOSESIAN |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 2/28/2024 | RAUL OLAGI |
| Permit Finaled | 3/28/2024 | DANIEL ORRANTE |
| CofO Issued | 3/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/25/2023 | COLIN LOREDO |
| ZA Case | Cleared | 2/1/2023 | DANG NGUYEN |
| Low Impact Development | Cleared | 2/6/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/7/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 4/26/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/22/2023 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 6/22/2023 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 6/26/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 6/29/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 7/17/2023 | Approved | RAUL OLAGI |
| Sewer | 7/17/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/17/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 8/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 8/29/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 8/29/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 10/2/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 10/2/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 10/2/2023 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 10/2/2023 | Approved | RAUL OLAGI |
| Insulation | 10/6/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/6/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/6/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/12/2024 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Final | 2/12/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 2/12/2024 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 2/16/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/16/2024 | Approved | RAUL OLAGI |
| Final | 2/16/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/16/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 2/16/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/16/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/16/2024 | Approved | RAUL OLAGI |
| Final | 2/26/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Service/Power Release | 2/26/2024 | Approved | CRAIG DAVIS |
| Final | 2/28/2024 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 2/28/2024 | Approved | RAUL OLAGI |