861-863 W 57TH ST 90037
Certificate Information: 861-863 W 57TH ST 90037
- Application / Permit
- 22010-20000-05940
- Plan Check / Job No.
- B22VN17855
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *EPLAN* NEW 2 STORY DUPLEX WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | SELLA BENYAMIN |
| Corrections Issued | 12/20/2022 | SELLA BENYAMIN |
| Quality Review Completed | 12/21/2022 | STEVEN KIM |
| Plan Check Approved | 2/10/2023 | SELLA BENYAMIN |
| Issued | 6/6/2023 | APPLICANT |
| CofO in Progress | 12/11/2023 | SABAS ALONSO |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/28/2022 | ERNEST TSE |
| Address approval | Cleared | 12/30/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2023 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 1/9/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/24/2023 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 1/25/2023 | MATTHEW CRAIG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 7/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 7/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 7/20/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/30/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 8/30/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/30/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/31/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 8/31/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/31/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 8/31/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 9/6/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 9/6/2023 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 9/25/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/25/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/9/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Final | 11/21/2023 | Approved | SABAS ALONSO |
| Final | 11/21/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/21/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 11/21/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/21/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/21/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 11/21/2023 | Approved | SABAS ALONSO |
| Final | 11/29/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 11/29/2023 | Approved | SABAS ALONSO |
| Final | 12/4/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 12/4/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/8/2023 | OK to Issue CofO | SABAS ALONSO |