22702 W CALVERT ST 91367

Certificate Information: 22702 W CALVERT ST 91367

Application / Permit
22010-20000-05938
Plan Check / Job No.
B22VN17849
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan 1/2 New detached ADU per LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 MARCELA FRANQUEZ
Corrections Issued 1/10/2023 MARCELA FRANQUEZ
Quality Review Completed 1/19/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 5/9/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 7/12/2023 MARCELA FRANQUEZ
Plan Check Approved 8/4/2023 MARCELA FRANQUEZ
Issued 8/30/2023 APPLICANT
CofO in Progress 9/13/2024 TROY SANDERS
Permit Finaled 10/1/2024 JOHN JANSON
CofO Issued 10/1/2024 JOHN JANSON
Permit Finaled 10/1/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/18/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/18/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 1/27/2023 KIRK LINKLATER
Hydrant and Access approval Cleared 4/18/2023 KURT CORRAL
Sewer availability Cleared 6/20/2023 COLIN LOREDO
Low Impact Development Cleared 6/30/2023 ERNEST TSE
GPI Written Notices Cleared 7/12/2023 MARCELA FRANQUEZ
Roof/Waste drainage to street Cleared 7/26/2023 ROMAN GUTIERREZ

Contact Information

Contractor Build 4 You Inc; Lic. No.: 914440-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/5/2023 Partial Approval TROY SANDERS
Deputy Drilled-In Anchors 9/13/2023 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 9/18/2023 Approved TROY SANDERS
Deputy Wood Construction 11/13/2023 Conditional Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval TROY SANDERS
Interior/Exterior Lathing 1/8/2024 Corrections Issued HENRY KIM
Shower Pan 1/8/2024 Approved HENRY KIM
BUILDING-Rough-Frame 1/10/2024 Approved TROY SANDERS
Green Building Rough 1/10/2024 Approved TROY SANDERS
Interior/Exterior Lathing 1/10/2024 Partial Approval TROY SANDERS
Shower Pan 1/10/2024 Approved TROY SANDERS
Verify Sprinkler Sign Off 1/10/2024 Approved TROY SANDERS
Insulation 1/12/2024 Approved TROY SANDERS
Drywall Nailing 1/18/2024 Approved TROY SANDERS
Interior/Exterior Lathing 1/18/2024 Partial Approval TROY SANDERS
Sewer 4/8/2024 Not Ready for Inspection TROY SANDERS
Sewer 4/11/2024 Approved TROY SANDERS
HVAC-Final 6/12/2024 Approved TROY SANDERS
Final 6/28/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 6/28/2024 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready GEVORK IPCHYAN
Service/Power Release 6/28/2024 Not Ready for Inspection GEVORK IPCHYAN
Smoke Detectors 6/28/2024 Not Ready for Inspection GEVORK IPCHYAN
Final 7/8/2024 Not Ready for Inspection TROY SANDERS
Green Building Final 7/8/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved TROY SANDERS
Service/Power Release 7/8/2024 Approved TROY SANDERS
Smoke Detectors 7/8/2024 Approved TROY SANDERS
Final 9/13/2024 OK to Issue CofO TROY SANDERS
Service/Power Release 9/27/2024 Approved TROY SANDERS