24219 W HILLHURST DR 91307
Certificate Information: 24219 W HILLHURST DR 91307
- Application / Permit
- 22010-20000-05925
- Plan Check / Job No.
- B22VN17816
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 15'-10" X 26'-10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | SELLA BENYAMIN |
| Corrections Issued | 12/13/2022 | SELLA BENYAMIN |
| Quality Review Completed | 12/16/2022 | STEVEN KIM |
| Building Plans Picked Up | 12/19/2022 | APPLICANT |
| Plan Check Approved | 2/16/2023 | SELLA BENYAMIN |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 10/30/2023 | CHRIS CHRISTENSEN |
| CofO in Progress | 11/17/2023 | HORACE FULTZ |
| CofO in Progress | 1/3/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
| CofO Issued | 5/6/2024 | JOHN JANSON |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/19/2023 | MEGAN GODINEZ |
| Address approval | Cleared | 2/1/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 2/6/2023 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 2/16/2023 | SELLA BENYAMIN |
Contact Information
| Contractor | Y S K Construction Group Inc; Lic. No.: 1056716-B | 24016 HILL HURST DR WEST HILLS, CA 91307 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/6/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 6/6/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 6/26/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/26/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 6/26/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/30/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/30/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Insulation | 6/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/19/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/19/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/19/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/27/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 9/21/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 9/21/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 9/21/2023 | Not Required | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/21/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 10/27/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |