19120 W STRATHERN ST 91335
Certificate Information: 19120 W STRATHERN ST 91335
- Application / Permit
- 22010-20000-05909
- Plan Check / Job No.
- B22VN17794
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan New 32' X 60' ONE STORY SFD PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21., NFPA-13R FIRE SPRINKLERS REQURIED THOUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/25/2023
- Issuing Office
- Current Status
- CofO Issued on 6/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | RARES BODEA |
| Corrections Issued | 12/19/2022 | RARES BODEA |
| Quality Review Completed | 12/21/2022 | STEVEN KIM |
| Applicant returned to address corrections | 9/26/2023 | RARES BODEA |
| Plan Check Approved | 9/28/2023 | RARES BODEA |
| Plan Check Approved | 10/23/2023 | RARES BODEA |
| No Progress | 10/23/2023 | RARES BODEA |
| Plan Check Approved | 10/23/2023 | RARES BODEA |
| Issued | 10/25/2023 | APPLICANT |
| CofO in Progress | 3/10/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 6/2/2025 | JOHN JANSON |
| CofO Issued | 6/2/2025 | JOHN JANSON |
| Permit Finaled | 6/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/21/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/25/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/17/2023 | KURT CORRAL |
| Sewer availability | Cleared | 7/25/2023 | CARLOS AGUILERA |
| Address approval | Cleared | 7/26/2023 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 8/10/2023 | MAYELA VILLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2023 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 11/8/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 12/11/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 12/11/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 12/18/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/15/2024 | Corrections Issued | JEFFREY BULL |
| ELECTRICAL-Rough | 3/15/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 3/15/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 3/15/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 3/15/2024 | Approved | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 3/15/2024 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 3/15/2024 | Not Ready for Inspection | JEFFREY BULL |
| Shower Pan | 7/3/2024 | Approved | MORRIS JACKSON |
| Underground Mechanical | 7/8/2024 | Approved | JEFFREY BULL |
| Insulation | 7/15/2024 | Corrections Issued | JEFFREY BULL |
| Drywall Nailing | 8/9/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 12/12/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Final | 12/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 12/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 12/12/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 12/12/2024 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/23/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 12/23/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 12/23/2024 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/23/2024 | Approved | ARUTYUN MADATYAN |
| Final | 2/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/7/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/7/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 3/7/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/7/2025 | Approved | ARUTYUN MADATYAN |
| Special/Order Compliance | 4/9/2025 | Corrections Issued | ARUTYUN MADATYAN |